Notes for wing construction:
o
There must be a left and a right wing half are built
o
Ribs loudly before cutting out number overview.
o
The feet of the balsa ribs break off very easily and should therefore with great care treated
will. (Tip: the little feet can with thin superglue to be soaked in order to achieve a higher
strength. However, it must be ensured that the superglue doesn't get up to rib soaked. This
would later make removal of the feet difficult.)
1. Put the slipway together and open fix it to the building board (pins, spray glue or thin double
sided use tape). The two slipway parts are on the separation point with two small bevels
marked, these must be on the be on the same side (see picture).
The milled lettering "FLUG" indicate the direction of flight. The associated arrows
demonstrate also on the millings of the front little feet the plywood root ribs. The small millings
are for the ribs. It there are also larger millings, which later for the slipway ribs needed to build
the bottom will.
Page 13
2. #13 rib shaft.
Carefully move the two ribs put together and for control the profile course and the length the
use rib 12 (overlay). Then the two rib parts at the glue point on both sides thin superglue wet.
o Setting up the ribs. Before the positioning the ribs in the slipway these should be plastered. It
comes with rib # 1 on the root rib position began, then all other ribs in increasing order set up
and fixed.
3. The rib spacing from # 16 to # 17 is about half of the other rib spacing. All ribs must be
perpendicular to the building board to be fixed (pins, with a small drop of glue fix).
Page 14
4. Base plate for spoiler and 3x3 Mandibular ridge between rib # 5 glue to # 8.
5. Lower spar chord jaw 6x3 mm stick together. The jaw ridge should be on two long edges are
chamfered to suck into the recess of the ribs to fit at the bonding make sure that the ribs are
vertical and the rib spacing is maintained.
6. Upper spar strap jaw 6x3 stick together. The jaw ridge should be on two long edges are
chamfered to suck into the recess of the ribs to fit at the bonding make sure that the ribs are
vertical and the rib spacing is maintained.
7. Attach the leading edge Balsa 6x6
Page 15
8. Prepare the upper cladding parts. Some parts need to be before the bonding are traded.
9. It comes with the front paneling began.