8. Start-up & Ready for Population
The Zella Pro Micro Data Centre is a PLUG N PLAY unit therefore once it has
been installed by a qualified contractor the Micro Data Centre is ready for use!
1.
Follow these steps to start up your unit:
z
Start-up the switchboard
z
Switch Mains Isolator A & B to the ON position
z
Switch Cooling System switch to the ON position only when the
cooling system has been commissioned.
Leave in the OFF position
until the air con contractor has installed.
z
Switch UPS switch to the ON position
z
Switch all remaining switches to the ON position
2.
Follow Pyrorack Commissioning steps from the installation manual.
3.
Populate the Micro Data Centre with your critical equipment and add
equipment labelling in PDView.
NOTE: Ensure adequate gaps are left between the equipment housed within
the Micro Data Centre to ensure an effective air-flow is maintained. The cooling
system will maintain the optimal cooling air-flow between the equipment if this
recommendation is adhered to.
NOTE:
DO NOT
exceed the cooling system’s recommended BTU/h specifications
(listed in the cooling system section) as this will overheat the equipment.