26 / 67
User’s Manual 3PH 100KTL-136KTL-HV
Rev. 1.0 24/02/2021
Identification: MD-AL-GI-00
Rev. 1.0 of 24/02/2021 - Application: GID
Figure 11 – Auxiliary handle position
3)
Lifting equipment.
Tighten the screws of two M12 rings into the inverter sides according to the instruction diagram below (Note:
M12 rings need self-preparation).
Figure 12 – Installation of rings
Fastened and tied the rope through two rings. Lifting inverter 50 mm above ground by using lifting
equipment, check the tightening device of the hoisting ring and rope. After confirming that the binding