SECTION 3 – HANDLING, STORAGE, INSTALLATION AND REASSEMBLY
FORM 155.35-ICOM2.EN.CE/GB (1018)
DATE: 10/30/2018
3
STRUCTURAL SUPPORT AND
INSTALLATION
Structural support of the unit must be provided for
maximum efficiency. Maintain adequate maintenance
space around the chiller-heater. Foundation bolts must
be installed in level concrete to secure the unit and pre-
vent shifting.
It is the customer's responsibility to furnish the founda-
tion bolts, nuts and washers. Rubber vibration isolator
pads must be fitted to the unit base before installation.
See
. The tolerance for leveling
is 1 inch in 1,000 inches or 1 mm in 1,000 mm.
Waterproof the floor on which the unit will
be installed in case of future leaks.
Apply thermal insulation to the chiller-heater. See the
installation instructions and
sure to install insulation on the exhaust gas duct outer
cover to prevent burns or a fire. A barrier fence to pre-
vent access may be used instead.
Dimensions can be found in
For the external dimensions of
the unit and foundation, see the full view of the unit
and the foundation drawing.
For serviceability and maintenance, leave a minimum
of 1,000 mm space on all sides of the chiller-heater. To
ensure there is adequate clearance for tube removal,
the space at the end should equal 1.25 x the length of
the unit.
INDOOR AND OUTDOOR INSTALLATION
This chiller-heater is designed to be used indoors. Ex-
posure to the elements may compromise the integrity
of the thermal insulation. The minimum allowable
temperature for outdoor installation is 0°C, provided
that the chiller-heater includes the cold ambient op-
tion.
Outdoor installations will be considered on a case-by-
case basis by a Johnson Controls Service Represen-
tative. Proper instruction for installation will be pro-
vided at that time.
When installing the unit indoors, have a specialized
company provide a suitable flue or smokestack, as well
as air supply and exhaust equipment. Insufficient air
supply or improper exhaust can cause oxygen starva-
tion and a fire. The interlock of the control panel should
be set up with a supply or exhaust fan to create a proper
draft.
Do not install a chimney near the air
supply.
ELECTRICAL
The electrical work must be performed in accordance
with the wiring diagrams, delivery specifications, and
technical standards for electrical equipment found in
. Use the specified
cables to complete the wiring. Be sure to fasten them
tightly to the appropriate terminals. Loose fitting cables
can cause the terminals to heat up. A fire or electrical
shock may occur as a result. Electrical work must be
supervised or completed by a Johnson Controls Service
Representative.
A ground fault (earth leakage) circuit
breaker is NOT installed for this chiller-
-heater unit. Be sure to install an adequate
ground fault circuit breaker at the pri-
mary side of the chiller-heater unit.
PRECAUTIONS FOR USE
Ventilate the storage area as much as possible to keep
the humidity low. Avoid storing the unit in an area
where the humidity is 95%RH or higher, and the tem-
perature is 40°C (104 °F) or higher. For more informa-
tion about long term-storage, refer to
Long-term Stor-
age Requirements (Form 50.20-NM1)
and
Long-term
Storage Checklist (Form 50.20-CL4).
Silica gel may be used on a temporary basis to dehu-
midify the control panel. Once the moisture is absorbed,
be sure to remove it. If you do not, the silica gel may
corrode the electrical parts of the control panel.