6. Protect the vapor fitting with a wet rag and braze the vapor

line connection. The nitrogen flow should be exiting the
system from the vapor service port connection. After This
connection has cooled, remove the nitrogen source from
the liquid fitting service port.

7. Evacuate the vapor line, indoor coil and the liquid line. See

“EVACUATION”  page 9.

NOTE: Do not use the system refrigerant in the outdoor unit

to purge or leak test.

8. Leak test all refrigerant piping connections including the serv-

ice port flare caps to be sure they are leak tight. DO NOT
OVERTIGHTEN (between 40 and 60 inch - lbs. maximum).

9. Do not remove the flare caps from the service ports except

when necessary for servicing the system.

CAUTION: Do not connect manifold gauges unless trouble is

suspected. Approximately 3/4 ounce of refrigerant
will be lost each time a standard manifold gauge is
connected.

10. Release refrigerant charge into the system. Open both the

liquid and vapor fittings by removing the plunger cap and
with an allen wrench back out counter-clockwise until valve
stem just touches retaining ring. See Base Valve Connec-
tion Precautions.

11. The sweat connect outdoor unit contains enough refriger-

ant charge for a matched indoor coil  and 15 feet of tubing.
Refer to the Table 4 for the amount of additional charge
required for some mix-matched indoor coils. Additional
charge for lines longer than 15 feet is shown in Table 5. If
additional charge is required, see recommended charging
methods.

ROOM THERMOSTAT

Heat pump units must use one of the specific thermostats
approved for use with these heat pump systems. The cooling
and heating anticipators are non-adjustable in these thermo-
stats.

The thermostat should be located about 5 ft. above the floor,
where it will be exposed to normal room air circulation. Do not
place it on an outside wall or where it is exposed to the radiant
effect from exposed glass or appliances, drafts from outside
doors or supply air grilles.

Mount the thermostat and route the 24-volt control wiring (NEC
Class 2) from the thermostat to the indoor and outdoor units.
To eliminate erratic operation, seal the hole in the wall at the
thermostat with permagum or equivalent to prevent air drafts
affecting the anticipators in the thermostat.

Route the control wiring into the outdoor unit through the hole
provided. Connect the control wiring, see Figure 4 or 5 for
Typical Field Wiring.

EVACUATION

It will be necessary to evacuate the system if the unit has
developed a leak during shipment or was, for any other reason,

opened to the atmosphere. If a leak is suspected, leak test to
locate the leak. Repair the leak and test again.

WARNING: Never attempt to repair any brazed connections

while the system is under pressure. Personal injury
could result.

To verify if the system has no leaks, simply close the valve to
the vacuum pump suction to isolate the pump and hold the
system under vacuum. Watch the micron guage for a few
minutes. If the micron gauge indicates a steady and continuous
rise, it’s an indication of a leak. If the gauge shows a rise, then
levels off after a few minutes and remains fairly constant, its an
indication that the system is leak free but still contains moisture
and may require further evacation if the reading is above 500
microns.

SYSTEM CHARGE

CAUTION: Refrigerant charging should only be carried out by

a qualified air conditioning contractor with proper
certification.

The factory charge in the outdoor unit is listed in Table 4 and
includes enough charge for the unit and a  matched indoor coil.
Sweat connect units also include sufficient charge for 15 feet
of lines. Pre-charged line lengths are factory charged with the
correct amount of refrigerant required.

Sweat connect installations over 15 feet long and some indoor
coil matches may require some additional charge. Table 5  lists
the amount of any additional refrigerant required.

The “TOTAL SYSTEM CHARGE” must be permanently
stamped on the unit data plate.

Total system charge is determined as follows:

1. Determine the outdoor unit charge from Table 4.

2. Determine indoor coil adjustment from Table 4.

3. Calculate the line charge with the factors in Table 5.

a) Calculate total length of pre-charged lines for quick

connect units.

b) Calculate over 15 feet of sweat lines for sweat connect

units.

NOTE: The charge for pre-charged lines should be included

in the system charge shown on the data plate but need
not be added to the system. If sweat connect lines are
used, the line charge over 15 feet should be included
on the data plate and must be added to the system.

4. Total system charge = item 1 + item 2 + item 3.

5. Permanently stamp the unit data plate with the total amount

of refrigerant in the system.

LIQUID OD

VAPOR OD

R-22 CHARGE OZ./FT.

3

8

5

8

0.66

3

8

3

4

0.68

3

8

7

8

0.70

TABLE 5 - REFRIGERANT LINE CHARGES

515.26-N5Y

Unitary Products Group

9

Summary of Contents for E9FD018 Series

Page 1: ...priate indoor unit air moving system and accessories Installer should pay particular attention to the words NOTE CAUTION and WARNING NOTES are intended to clarify or make the installation easier CAUTI...

Page 2: ...cause personal injury Remember that condensate will drip from the unit coils during heat and defrost cycles and that this condensate will freezewhen thetemperature ofthe outdoor air is below 32 F Ele...

Page 3: ...SQ FT 14 2 15 1 15 1 17 0 20 20 24 ROWS DEEP 1 1 1 1 1 1 2 FIN INCH 13 18 18 20 13 16 13 LIQUID LINE OD 3 8 3 8 3 8 3 8 3 8 3 8 3 8 VAPOR LINE OD 5 8 5 8 3 4 3 4 7 8 7 8 7 8 OPERATING WEIGHT LBS 140 1...

Page 4: ...ressor where theheater isinstalled The heater should be energized for at least 8 hours before the thermostat is set to operate the compressor CAUTION An attempt to start the compressor without at leas...

Page 5: ...or C L or X T E FIELD INSTALLED JUMPER 1 2 2 BLK YEL ORG WHT BRN X FIGURE 4 TYPICAL 1 FIELD WIRING Air Handler Electric Heat Y O W1 or 66 W GRD LUG DEFROST CONTROL CONTACTOR GRD SCREW M R C 53 or W3 R...

Page 6: ...es with as few bends as possible Care must be taken not to damage the couplings or kink the tubing Care must also be used to isolate the refrigerant lines to minimize noise transmission from the equip...

Page 7: ...e coil instruction for details to change the orifice in the coil QUICK CONNECT SYSTEMS Indoor coils and outdoor units are to be connected with pre charged interconnecting tubing specified for the spli...

Page 8: ...it as shown in Figure 9 Also protect all painted surfaces and insulation during brazing After brazing cool joint with wet rag WARNING Thisis not a backseating valve The service access port has a valv...

Page 9: ...ovided Connect the control wiring see Figure 4 or 5 for Typical Field Wiring EVACUATION It will be necessary to evacuate the system if the unit has developed a leak during shipment or was for any othe...

Page 10: ...t through blower relay to provide blower operation 4 System will cycle with thermostat demand to provide cool ing as needed WITH POWER TO UNIT AND THERMOSTAT IN HEATING POSITION 1 Reversing valve is d...

Page 11: ...l illumi nate on the thermostat To reset the lockout turn the indoor thermostat s system switch to OFF then back to the selected mode within 5 second OR disconnect the power to the trans former for at...

Page 12: ...ting discharging warm air from the ducts 3 The vapor line at the outdoor unitwill feel warm to the touch 4 The liquid line at the outdoor unit will feel cool to the touch NOTICE TO OWNER If lockout oc...

Reviews: