background image

 

IM11Y01B01-12E-A 

 2nd Edition 

 
Window Purge Gas Flow Adjustment

 – While there is no specific formula for this purge gas flow 

rate (due to the many variables/complexity), we include the following information that might help 
optimize the window purge gas flow rates actually at site. As mentioned in the User’s Guide, the 
window purge flow rate can vary by application from as little as 5 lts./min up to as much as 50 
lts./min for typical process applications.  
 
There are a couple of methods that can be used to help establish a suitable flow rate.  
 
For relatively short optical path lengths (such as process O2 measurements) if there is too much 
flow the purge gas will protrude/mix into the process gas slightly and therefore possibly cause a 
slightly shorter actual optical path length (

readings lower than expected

). Conversely, if there is too 

little window purge flow the process gas may protrude/mix with the purge gas (worst case 
contaminate the windows) in the connection nozzle and possibly cause a slightly longer actual 
optical path (

readings higher than expected

). 

 
One method that can be used (if the process gas is not excessively dirty or wet) would be to 
measure the process gas without purge for a short period of time. Before starting this test, the 
process measurement (O2 concentration) should be relatively stable and not expected to change 
within a few minutes. First, establish the distance between the launch unit window and the detect 
unit window and enter this value as the Process Path Length (under Advanced Menu, Configure). 
Then stop the process window purge gas flow to both the launch and detect units while observing 
the transmission – note, if there is a sudden large decrease in transmission then probably 
contamination/fouling has occurred on the windows! Wait  for the process reading to stabilize (i.e. 
the process gas has filled the nozzle and alignment bellows sections up to each window), take note 
of the measurement value and resume some window purge flow. Change the Process Path Length 
back to the normal value and now resume/adjust the launch and detect unit window purges until 
the process reading matches the value noted when there was no purge flow. If the transmission 
does not return to its original value then the process windows will have to be cleaned to ensure 
optimal operation. It is best to repeat this procedure two or three times to ensure repeatable results 
that establish confidence in the readings. This can be repeated at any time at a later date to verify 
the process readings. 
 
A similar method can also be used by comparing ratios of the path lengths and measurements with 
and without window purge flow. Using the analyzers integral Trend function, observe the 
measurement values when both launch and detect window purge gas flows are simultaneously 
stopped (for approx. 30 seconds or until the reading stabilizes) and then resume window purge 
flow back to the initial flow rates. As with the other method, observe the transmission – note, if 
there is a sudden large decrease in transmission then probably contamination/fouling has occurred 
on the windows! Once the process measurement has re-stabilized with window purge gas flow, 
repeat the simultaneous stopping of window purge gas flow. Repeat this several times until the 
trend screen clearly shows repeatable measurement results with and without window purge. If the 
transmission does not return to its original value then the process windows will have to be cleaned 
to ensure optimal operation. The ratio of these two measurements can now be established based 
on the repeatable results obtained. Establish the distance between the launch unit window and the 
detect unit window and calculate the ratio with respect to the normal Process Path Length. The 
ratio of ‘measurement without purge gas to measurement with purge gas’ should be equal to ‘path 
length window-window to process path length’ – thus indicating that the connection nozzles are 
purged correctly. 

Summary of Contents for TDLS200

Page 1: ...1 IM11Y01B01 12E A 2nd Edition TDLS200 Tunable Diode Laser Analyzer Addendum Instruction Manual Furnaces Heaters Large Scale Combustion...

Page 2: ...ns that may exist or potentially exist Please take appropriate action to prevent ALL POTENTIAL ACCIDENTS AVOID SHOCK AND IMPACT TO THE ANALYZER THE LASERS CAN BE PERMANENTLY DAMAGED Laser Safety Class...

Page 3: ...3 IM11Y01B01 12E A 2nd Edition within this addendum supersede any conflicting statement contained within the standard Users Guide...

Page 4: ...00C 1475F Combustion flue OPL 1 10m 33ft atmospheric pressure 500C 930F o Oxygen 0 21 for control or monitoring o CO 0 5 000ppm for control monitoring or safety CH4 0 5 breakthrough monitoring and or...

Page 5: ...is almost impossible to keep good alignment with varying ambient and process conditions especially during cold starts and shut downs the most extreme thermal changes on the mechanical structures To re...

Page 6: ...analyzer is to be installed is to vary by more than 10o C 18o F then an Active input signal should be used for compensation Ensure the analyzer has been selected and configured to suit the maximum ope...

Page 7: ...s sections up to each window take note of the measurement value and resume some window purge flow Change the Process Path Length back to the normal value and now resume adjust the launch and detect un...

Page 8: ...uch equipment installation Appropriate hazardous area if applicable precautions Owner Company best practice and engineering standards Access for personnel to stand in front of launch and Detect Units...

Page 9: ...9 IM11Y01B01 12E A 2nd Edition Clearance for Launch Unit Ensure there is sufficient clearance and access for the Launch unit...

Page 10: ...10 IM11Y01B01 12E A 2nd Edition Clearance for Detect Unit Ensure there is sufficient clearance and access for the Detect unit...

Page 11: ...Dimensions for combustion process interface devices Above 3 150 ANSI RF option for Launch unit alignment bellows Above 4 150 ANSI RF option for Launch unit alignment bellows Above 4 150 ANSI RF Large...

Page 12: ...is maintained at all times Rigid mounting for the process flanges is highly recommended to ensure alignment is maintained In situations where the process flanges are mounted to these thin and flexible...

Page 13: ...t and Line Up The Launch and Detect units are provided with alignment mechanisms that allow for some manual adjustment of the laser beam direction in both planes It is however recommended that the fol...

Page 14: ...14 IM11Y01B01 12E A 2nd Edition...

Page 15: ...15 IM11Y01B01 12E A 2nd Edition...

Page 16: ...the walls and the adjacent heater furnace structural steel as shown conceptually below Note horizontal vertical bracing tied to the adjacent structural steel and walls of the unit Diagram below shows...

Page 17: ...ptics at distances less than 10 from the furnace wall The above preferred method may not be possible in every site specific situation The actual dimensions may have to be adjusted to suit the practica...

Page 18: ...ed method and case B below shows an alternative method if the preferred method cannot be accommodated at the particular site installations Above Preferred angle mounting above Alternate angle mounting...

Page 19: ...ng the actual purge flows ensure the lines have been blown out to remove all debris dirt oil water and other media that could contaminate the optical surfaces and impaired the optical transmission mea...

Page 20: ...ing the transmission strength while adjusting the top bottom and left right nuts on the alignment bellows The adjustments are performed on one axis at a time The intent is to use the alignment bellows...

Page 21: ...21 IM11Y01B01 12E A 2nd Edition...

Page 22: ...22 IM11Y01B01 12E A 2nd Edition Above Zero Transmission No Signal Above 0 2 Transmission small signal...

Page 23: ...s by starting at the launch end maximize the signal using the transmission signal and value by moving the launch around using the alignment bellows Once maximum signal is achieved move to the detect e...

Page 24: ...es to ensure maximum transmission Once maximum transmission is achieved move to the next step and ensure the laser is centered This is done by sweeping the laser across the detector in both the horizo...

Page 25: ...25 IM11Y01B01 12E A 2nd Edition...

Page 26: ...26 IM11Y01B01 12E A 2nd Edition...

Page 27: ...27 IM11Y01B01 12E A 2nd Edition...

Page 28: ...scope or scope meter Please read the entire procedure before starting work and ask your local Yokogawa service group for further information if required This procedure can also be performed by local Y...

Page 29: ...29 IM11Y01B01 12E A 2nd Edition...

Page 30: ...30 IM11Y01B01 12E A 2nd Edition...

Page 31: ...31 IM11Y01B01 12E A 2nd Edition...

Page 32: ...be very small initially as low as 0 1 volts move to the detect end and using the method described in the previous slide move the LAO detect assembly around until maximum signal is achieved The launch...

Page 33: ...33 IM11Y01B01 12E A 2nd Edition...

Page 34: ...34 IM11Y01B01 12E A 2nd Edition...

Page 35: ...35 IM11Y01B01 12E A 2nd Edition...

Page 36: ...ice the detector gain needs to be adjusted to achieve the best analyzer performance This document gives the guidance and procedures to adjust the detector board gain for services and customers after t...

Page 37: ...ase keep the original R22 and R23 in the resistor bag as they can be used for future offline calibration 6 Optimize the analyzer alignment for both the launch and detector sides Stop the alignment if...

Page 38: ...cuit on the board i e loose wires or touching adjacent components with pliers or tool used to remove resistor How to install a new gain resistor First try the new resistor by molding and clipping the...

Page 39: ...wa Office Yokogawa Distributor or Yokogawa Sales Representative or Yokogawa Laser Analysis Division directly as listed below Yokogawa Laser Analysis Division 910 Gemini Street Houston Texas 77058 USA...

Reviews: