background image

38 

 

IM11Y01B01-12E-A 

 2nd Edition 

high-process-temperature analyzer (with a capacitor on R3), the raw detector signal is within 
requirement if 

MIN

 is between 

-4.0

 and 

-8.5

 

c.

 

If the raw detector signal is too low (other than a and b), change either R22 or R23 to the next 
greater value available in the resistor bag, and then go back to 

STEP 7

. How to decide which 

resistor to change: 

i.

 

If  the  current  R22  value  is  greater  than  the  current  R23  value,  change  R23  to  the 
next greater value available in the resistor bag. 

ii.

 

If the current R22 value is same as the current R23 value, change R22 to the next 
greater value available in the resistor bag. 

iii.

 

If the current R22 and R23 are already 24.3kΩ (the greatest value available in the 
resistor bag), please contact Yokogawa for assistance. 

 

9.

 

Close  the  detector  enclosure.  Write  down  the  final  values  of  R21,  R22  and  R23  below  for  record. 
R21 = ____________; R22 = ____________; R23 = ____________. 

 

10.

 

Enter  these  new  resistor  values  into  the  analyzer  configuration  under  Advanced  Menu  > 
Configure  >  System  >  Adjustable  Resistors  >  Detect  –  R21,  Detect  –  R22,  and  Detect  –  R23.  All 
resistor values are entered in K ohm unit. 

 

11.

 

Keep  the  resistor  bag  and  this  procedure  document  by  customer.  DO  NOT  leave  them  in  the 
detector box or throw them away. 

TIPS 

 

 

How to remove a gain resistor?

 On the detector board, find the location of the gain resistor. Please 

note that the resistor is not soldered but resting in sockets. Carefully remove the resistor from the 
socket  on  the  board. 

Since  the  analyzer  is  still  powered  on,  please  take  extreme  caution  to 

prevent a short circuit on the board, i.e. loose wires or touching adjacent components with pliers 
or tool used to remove resistor.

 

 

 

How  to  install  a  new  gain  resistor?

  First  try  the  new  resistor  by  molding  and  clipping  the  resistor 

leads to fit into the socket. Then carefully insert the resistor into the socket on the detector board. 

Since the analyzer is still powered on, please take extreme caution to prevent a short circuit on 
the  board,  i.e.  loose  wires  or  touching  adjacent  components  with  pliers  or  tool  used  to  install 
resistor.

 

 

 

Please keep the factory/original gain resistors in the resistor bag as they will be used in the future 
for offline calibration or test. 

 

 

The  raw  detector  signal  (

MAX-MIN

)  is  proportional  to  R21·R22·R23.  Usually  R21  is  maintained  as 

factory value. R22 and R23 are optimized in the field. We want to avoid the situation where one of 
R22 and R23 resistors has extreme low resistance and the other one has extreme high resistance. 
The  analyzer  gives  best  performance  when  R22  and  R23  are  balanced.  Based  on  this  relation 
between raw detector signal and gain resistors, service technician or customer can select R22 and 
R23 faster with the help of a calculator. 

 

 

Multiple alignment actions might be needed if Detector Signal High fault happens. Reduce the gain 
resistor first as described in 

STEP 8-a

, and then optimize the alignment again. 

 

NOTE: If the alignment has been performed on a ‘cold’ (shut-down) heater/furnace, then it is 
highly recommended when the heater/furnace is at normal operating temperature, the 
transmission/alignment be checked again to ensure >10% (ideally >25%) transmission exists and 
that there are no alarms. Validation gas should also be introduced through the validation cell to 
ensure peak response, especially if a line-locking gas is not being used.

Summary of Contents for TDLS200

Page 1: ...1 IM11Y01B01 12E A 2nd Edition TDLS200 Tunable Diode Laser Analyzer Addendum Instruction Manual Furnaces Heaters Large Scale Combustion...

Page 2: ...ns that may exist or potentially exist Please take appropriate action to prevent ALL POTENTIAL ACCIDENTS AVOID SHOCK AND IMPACT TO THE ANALYZER THE LASERS CAN BE PERMANENTLY DAMAGED Laser Safety Class...

Page 3: ...3 IM11Y01B01 12E A 2nd Edition within this addendum supersede any conflicting statement contained within the standard Users Guide...

Page 4: ...00C 1475F Combustion flue OPL 1 10m 33ft atmospheric pressure 500C 930F o Oxygen 0 21 for control or monitoring o CO 0 5 000ppm for control monitoring or safety CH4 0 5 breakthrough monitoring and or...

Page 5: ...is almost impossible to keep good alignment with varying ambient and process conditions especially during cold starts and shut downs the most extreme thermal changes on the mechanical structures To re...

Page 6: ...analyzer is to be installed is to vary by more than 10o C 18o F then an Active input signal should be used for compensation Ensure the analyzer has been selected and configured to suit the maximum ope...

Page 7: ...s sections up to each window take note of the measurement value and resume some window purge flow Change the Process Path Length back to the normal value and now resume adjust the launch and detect un...

Page 8: ...uch equipment installation Appropriate hazardous area if applicable precautions Owner Company best practice and engineering standards Access for personnel to stand in front of launch and Detect Units...

Page 9: ...9 IM11Y01B01 12E A 2nd Edition Clearance for Launch Unit Ensure there is sufficient clearance and access for the Launch unit...

Page 10: ...10 IM11Y01B01 12E A 2nd Edition Clearance for Detect Unit Ensure there is sufficient clearance and access for the Detect unit...

Page 11: ...Dimensions for combustion process interface devices Above 3 150 ANSI RF option for Launch unit alignment bellows Above 4 150 ANSI RF option for Launch unit alignment bellows Above 4 150 ANSI RF Large...

Page 12: ...is maintained at all times Rigid mounting for the process flanges is highly recommended to ensure alignment is maintained In situations where the process flanges are mounted to these thin and flexible...

Page 13: ...t and Line Up The Launch and Detect units are provided with alignment mechanisms that allow for some manual adjustment of the laser beam direction in both planes It is however recommended that the fol...

Page 14: ...14 IM11Y01B01 12E A 2nd Edition...

Page 15: ...15 IM11Y01B01 12E A 2nd Edition...

Page 16: ...the walls and the adjacent heater furnace structural steel as shown conceptually below Note horizontal vertical bracing tied to the adjacent structural steel and walls of the unit Diagram below shows...

Page 17: ...ptics at distances less than 10 from the furnace wall The above preferred method may not be possible in every site specific situation The actual dimensions may have to be adjusted to suit the practica...

Page 18: ...ed method and case B below shows an alternative method if the preferred method cannot be accommodated at the particular site installations Above Preferred angle mounting above Alternate angle mounting...

Page 19: ...ng the actual purge flows ensure the lines have been blown out to remove all debris dirt oil water and other media that could contaminate the optical surfaces and impaired the optical transmission mea...

Page 20: ...ing the transmission strength while adjusting the top bottom and left right nuts on the alignment bellows The adjustments are performed on one axis at a time The intent is to use the alignment bellows...

Page 21: ...21 IM11Y01B01 12E A 2nd Edition...

Page 22: ...22 IM11Y01B01 12E A 2nd Edition Above Zero Transmission No Signal Above 0 2 Transmission small signal...

Page 23: ...s by starting at the launch end maximize the signal using the transmission signal and value by moving the launch around using the alignment bellows Once maximum signal is achieved move to the detect e...

Page 24: ...es to ensure maximum transmission Once maximum transmission is achieved move to the next step and ensure the laser is centered This is done by sweeping the laser across the detector in both the horizo...

Page 25: ...25 IM11Y01B01 12E A 2nd Edition...

Page 26: ...26 IM11Y01B01 12E A 2nd Edition...

Page 27: ...27 IM11Y01B01 12E A 2nd Edition...

Page 28: ...scope or scope meter Please read the entire procedure before starting work and ask your local Yokogawa service group for further information if required This procedure can also be performed by local Y...

Page 29: ...29 IM11Y01B01 12E A 2nd Edition...

Page 30: ...30 IM11Y01B01 12E A 2nd Edition...

Page 31: ...31 IM11Y01B01 12E A 2nd Edition...

Page 32: ...be very small initially as low as 0 1 volts move to the detect end and using the method described in the previous slide move the LAO detect assembly around until maximum signal is achieved The launch...

Page 33: ...33 IM11Y01B01 12E A 2nd Edition...

Page 34: ...34 IM11Y01B01 12E A 2nd Edition...

Page 35: ...35 IM11Y01B01 12E A 2nd Edition...

Page 36: ...ice the detector gain needs to be adjusted to achieve the best analyzer performance This document gives the guidance and procedures to adjust the detector board gain for services and customers after t...

Page 37: ...ase keep the original R22 and R23 in the resistor bag as they can be used for future offline calibration 6 Optimize the analyzer alignment for both the launch and detector sides Stop the alignment if...

Page 38: ...cuit on the board i e loose wires or touching adjacent components with pliers or tool used to remove resistor How to install a new gain resistor First try the new resistor by molding and clipping the...

Page 39: ...wa Office Yokogawa Distributor or Yokogawa Sales Representative or Yokogawa Laser Analysis Division directly as listed below Yokogawa Laser Analysis Division 910 Gemini Street Houston Texas 77058 USA...

Reviews: