4. INSTALLATION
4.4 Changing Integral Indicator
Direction
IMPORTANT
• Always turn OFF power and shut off and
release pressures before disassembly.
• For changing the integral indicator direction,
the transmitter must be removed to a non-
hazardous area.
An integtal indicator can be installed in the following
three directions, Refer to subsection 8.4 for attaching
and removing the integral indicator.
F0403.EPS
Figure 4.3
Integral Indicator Direction
4.5 Mounting the Flushing Con-
nection Ring
4.5.1 Mounting to Pressure Detector
Section
The flushing connection ring is mounted to high
pressure side pressure detector section as shown in
Figure 4.4.
At the factory shipment, the flushing connection ring is
already assembled and attached to high pressure side
process detector section.
F0404.EPS
Pressure-detector section
Drain/vent plug
Ring
Ring holder
Spiral gasket
View from pressure detector section side
Groove for installing
spiral gasket
Figure 4.4
Mounting to Pressure Detector Section
(1) Mount the ring holder on the ring and loosely
tighten the mounting screws.
(2) Place the spiral gasket in the ring groove. With the
ring correctly aligned and flush with the face of the
pressure detector, securely tighten each ring
holder’s mounting screws.
(3) Position the ring so that the drain/vent plugs are
aligned straight up and down.