Copyright | C6AM User Manual, Version 1.2.2
19
PV
Notes:
laying of power cables should be carried out in accordance with relevant national and
industrial standards and specifications including construction quality, process, and
technical standards.
Cable selection specification shall be selected according to the type, power, voltage
and current level of the equipment and the number of equipment installed.
When cables are laid, they are strictly forbidden to be exposed. Cable bridges, line
pipes and directly buried cabling should be used based on the environment and
installation location.
When the cables are directly buried, the depth of burying shall not be less than 0.8m
because of the frost-proof.
When plastic pipes are used for power distribution, flame-retardant type, and wall
thickness >2.0mm shall be adopted. When a steel pipe is used for underground pipe
wiring, the wall thickness is >2.5mm and anticorrosive treatment is carried out.
The selection of power cable specifications should be selected according to the
installation environment and fire requirements.
round
C Pipe
Figure 4.3.2
4.3.2 Optional Stainless Steel Frame
The C6AM charging station can be fixed onto the flat ground with a stainless-steel frame. The
ground shall be concrete or at equal level of hardness. Please refer to Figure 4.3.3, Figure 4.3.4,
and Figure 4.3.5 for the details of instruction.