COMMISSIONING REPORT
6 720 641 467 (2010/01)
52
16 COMMISSIONING REPORT
Customer/system user:
System installer:
Type of heat pump:
Heat pump serial number:
Commissioning date:
HWDU serial number:
Other system components:
Outdoor sensor T2
Room temperature sensor T5
Hot water cylinder temperature sensor T3
Others:
Points to be checked prior to commissioning
Heating system: Filled
Checked
Electric heater set to 4.5 kW: Set
Checked
Filters: Checked
Cleaned
Sight glass: Checked
Comments:
Heating system pump G1A/G1B working correctly:
Heat carrier pump G2 working correctly:
Operating temperature after 10 minutes in heating/DHW mode:
Heat flow out T8:.................. °C
Heat return in T9:.................. °C
Sensor condensor temp T10:................... °C
Refrigerant temp T11:.................. °C
Defrost sensor T12:................... °C
System pressure levels checked
...............................................................................................................................
Functional test carried out
........................................................................................................................................
Ensure that primary circuit has been correctly flushed
.............................................................................................
Check fan operation on outdoor unit
........................................................................................................................
Check for insulation of pipe work
.............................................................................................................................
Check that CANbus is fitted correctly
.......................................................................................................................
Check term switches positioned correctly
................................................................................................................
Check condensation drain operates
.........................................................................................................................
Hot water peak set
....................................................................................................................................................
Electricity reading on the house taken
......................................................................................................................
The instructions about how to use the heat pump have been given to the client / to the user
...................................................................................................................................................................................
Documentation about the heat pump has been handed over:......................................................................................
Date and signature of system installer:
Tab. 14