Abridged instructions OKTOPUS
GL-K800
1
Coupling to the crane
(1) For wall or roof installation attach the OKTOPUS
to the crane hook.
(2) If necessary erect scaffolding for the installation.
2
Putting the OKTOPUS
into operation
(1) Place the OKTOPUS
®
on the load!
(2) Turn the main switch to the "ON“ position!
(3) Push the switch SUCTION / RELEASE toward SUCTION!
(4) Check the charge level of the battery on the charge indicator:
•
if the yellow LEDs lights up, the device is ready for operation,
•
if the yellow LEDs flash or the red LED already lights up charge the battery.
(5) Check the vacuum pressure on the vacuum gauges (permissible green range -0.65
to -0.9 bar):
•
if the pressure is on one or both gauges in the red range, the alarm is activated
and the vacuum must first build up.
•
if the pressure is on both gauges in the green range, the unit is ready for
operation!
3
Instructions for use
(1) Preparing the construction elements:
•
Check the element surface on the contact areas: smooth, impervious to air,
clean, dry, without protective film.
(2) Lifting the elements:
•
Place the OKTOPUS
®
on the element.
•
Push the switch SUCTION / RELEASE toward SUCTION!
(3)
Positioning the elements:
•
Raise/erect the elements with the lifting operation of the crane.
•
Position the elements by driving and lifting movement of the crane and
simultaneous manual guiding of the element by the fitter.
•
Fasten the elements to the wall surface.
(4) Release the OKTOPUS
®
from the elements:
•
raise the switch SUCTION / RELEASE somewhat and push it toward RELEASE.
4
Taking the unit out of operation
•
Lower the OKTOPUS
®
with the crane.
•
Cut the connection between OKTOPUS
®
and crane.
•
Turn the main switch to the “OFF” position.
•
If the unit is to be taken out of operation for several days, connect an operational
charger.