Installation and operating instructions Wilo-DrainLift XL

33

7.4.1 Switchgear mains connection

• Mains connection: 3~400 V + N + PE (L1, L2, L3, N, PE)
• Version: Switchgear with CEE plug pre-installed [in accordance with VDE 0623 

in Germany].

• Connect the clockwise rotating field

7.4.2 Connection of the pumps (Fig. 10)

• The pumps are to be wired with the switchgear.
• Undo the housing screws and remove the terminal cover.
• Guide the cable ends of the pump connection line through the threaded cable connections.
• Wire up the cable ends in accordance with the marking on the terminal strips and the spec-

ifications in the wiring diagram:
• Mains connection of the pump 1 to the terminals 27, 28 and 29. 
• Mains connection of the pump 2 to the terminals 34, 35 and 36. 
• Earth conductor to the remaining PE terminal.
• Connection of the thermal winding contact (WSK) pump 1 to terminals 31 and 32
• Connection of the thermal winding contact (WSK) pump 2 to terminals 38 and 39

7.4.3 Connection of the level sensor (Fig. 11)

• The level sensor must be wired directly with the breakdown barrier. 
• Undo the housing screws and remove the cover.
• Feed the cable ends from the level sensor through the cable bushing.
• Wire up the cable ends according to the information in the wiring diagram:

• Brown wire (+) to terminal 23 (+) of the breakdown barrier
• Green wire (-) to terminal 13 (-) of the breakdown barrier
• Blue wire (shield) to PE terminal
• The cable of the breakdown barrier with a signal level of 4-20 mA must be connected to 

terminals 25 (+) and 26 (–) in the switchgear using two-wire technology.

• Close the cover of the breakdown barrier and the switchgear, and tighten the housing 

screws

DANGER! Danger of explosion!
If a level sensor is used in potentially explosive areas there is a danger of explosion.

• Always use a breakdown barrier (Zener barrier) between the switchgear and the level 

sensor in potentially explosive areas. 
Observe the safety instructions in the operating instructions for the breakdown bar-
rier.

NOTE: 
Observe the correct polarity when connecting the level sensor and the breakdown barrier. 

7.4.4 Alarm signal connection

The DrainLift XL system is factory-fitted with an acoustic signal transmitter in the switch-
gear. 
An external alarm switchgear, a horn or a flash light can be connected via a potential-free 
contact (SSM) in the switchgear. Contact load:

• Permitted minimum: 12 V DC, 10 mA
• Permitted maximum: 250 V AC, 1 A

DANGER! Risk of fatal injury!
There is a danger of electric shock by touching live components when working on the 
open switchgear. 
This work may only be carried out by qualified personnel.
To connect the alarm signal, switch off the device so that it is voltage-free and secure 
it against being switched back on again by unauthorised persons.

Comply with the Installation and operating instructions of the DrainControl PL2 switch-
gear!

• Remove the power plug! 
• Open the cover of the switchgear.
• Remove the protective cover from the threaded cable connection.
• Feed the cable through the screwed connection and connect it to the potential-free alarm 

contact in accordance with the wiring diagram.

• After connecting the cable for the alarm signal, close the cover of the switchgear and 

tighten the threaded cable connection.

• Plug in the mains plug again.

Refer to the operating instructions of the switchgear for a detailed description of the con-
nection options and operation.

Summary of Contents for DrainLift XL

Page 1: ...edieningsvoorschriften E Instrucciones de instalaci n y funcionamiento I Istruzioni di montaggio uso e manutenzione GR TR Montaj ve kullanma k lavuzu H Be p t si s zemeltet si utas t s PL Instrukcja m...

Page 2: ...Fig 10...

Page 3: ...Fig 11...

Page 4: ...etechnicianandthe responsible specialist operator before installation and commissioning It is not only the general safety instructions listed under the main point safety that must be adhered to but al...

Page 5: ...ilst the product is in operation Leakages e g from the shaft seals of hazardous fluids which are explosive toxic or hot must be led away so that no danger to persons or to the environment arises Natio...

Page 6: ...s such as heavy metals biocides pesticides acids bases salts cleaning agents and disinfectants dish washing or laundry detergents and such which have a high degree of foam formation or swimming pool w...

Page 7: ...ons Any use going over and beyond the intended use is considered to be improper 5 Product information 5 1 Type key Example DrainLift XL 2 25 3 DrainLift Sewage lifting unit XL Size 2 2 double pump sys...

Page 8: ...detailed list and description see the cata logue price list The following accessories are available Flange piece DN 80 DN 80 100 1 pc DN 80 100 already included in scope of delivery DN 100 DN 150 for...

Page 9: ...the tank is switched on and the collected sewage is automatically pumped into the connected exter nal sewage line If the water level continues to rise the second pump is activated When the high water...

Page 10: ...Make sure the installation location is ventilated sufficiently 7 1 Preparing for installation CAUTION Risk of property damage Incorrect installation can result in damage to the product Only use qualif...

Page 11: ...not be subjected to any pipeline forces or torques The pipes including valves are to be fastened and supported in such a manner that neither tensile nor compressive forces are applied to the unit All...

Page 12: ...surge like water entry and strong air entry are avoided as much as possible It is possible to connect the inlet pipe into the vertical surface above the horizontal con nection surface Leave out the a...

Page 13: ...ightness of the pipe connection depends on this decisively Fig 6 Setting up the inlet port DN 150 DN 100 1 1 Define the position of the middle of the inlet and mark it Cut the hole using the keyhole s...

Page 14: ...Secure the venting pipe against slipping out using clamps and always install with a downward incline toward the unit 7 3 4 Emergency drain connection diaphragm hand pump It is always recommended to i...

Page 15: ...5 A slow DrainLift XL 2 15 25 A slow DrainLift XL 2 20 25 A slow DrainLift XL 2 25 25 A slow NOTE To increase the operational reliability it is mandatory for an automatic circuit breaker which disconn...

Page 16: ...arrier and the switchgear and tighten the housing screws DANGER Danger of explosion If a level sensor is used in potentially explosive areas there is a danger of explosion Always use a breakdown barri...

Page 17: ...e pressure pipeline is completely filled The filling level in the tank must not rise when the discharge piping is filled and the inlet closed If the filling level continues to rise the flap of the non...

Page 18: ...owing points in particularin case of deviations from the recommended settings The filling level probe must be in contact with the base of the tank According to EN 12056 4 the switching volume should b...

Page 19: ...ime of the pumps 8 3 Decommissioning The unit must be decommissioned prior to maintenance or dismantling work WARNING Risk of burns Depending on the operating status of the system the entire pump can...

Page 20: ...subjected to maintenance by experts in accordance with EN 12056 4 The intervals must not exceed year in the case of commercial companies year for units in multi family houses 1 year for units in singl...

Page 21: ...eposits in the pump and or tank 2 Incorrect direction of rotation Swap two phases of the current feed 3 Wear to inner parts impeller bearing Replace worn parts 4 Operating voltage too low 5 Running on...

Page 22: ...ion de la directive basse tension 2006 95 CE sont respect es conform ment appendice I no 1 5 1 de la directive CE relatives aux machines 2006 42 CE Elektromagnetische Vertr glichkeit Richtlinie 2004 1...

Page 23: ...nast puj cymi dokumentami Sm rnice ES pro strojn za zen 2006 42 ES dyrektyw maszynow WE 2006 42 WE EC 2006 42 EG C le t kaj c se bezpe nosti stanoven ve sm rnici o elektrick ch za zen ch n zk ho nap...

Page 24: ...Mather and Platt Pumps Ltd Pune 411019 T 91 20 27442100 service pun matherplatt co in Indonesia WILO Pumps Indonesia Jakarta Selatan 12140 T 62 21 7247676 citrawilo cbn net id Ireland WILO Engineering...

Page 25: ...henstra e 100 44263 Dortmund T 0231 4102 7900 T 01805 W I L O K D 9 4 5 6 5 3 F 0231 4102 7126 kundendienst wilo com T glich 7 18 Uhr erreichbar 24 Stunden Technische Notfallunterst tzung Kundendienst...

Reviews: