4.3 Burner installation
Only valid in Switzerland
When installing and operating the regulations of SVGW, VKF, local and Cantonal
regulations and the EKAS guideline (LPG Guideline Part 2) must be observed.
Remove mixing head [ch. 9.3].
Remove burner flange
1
from burner housing.
The burner in its standard version is designed for valve train connection from the
right. For gas valve train connection from the left the burner has to be installed ro-
tated by 180° [ch. 4.3.1]. To do this, additional conversion measures are required
[ch. 5.1.1].
Fit flange gasket
2
and burner flange
1
to the heat exchanger using screws
3
.
The aperture between combustion head and refractory should be filled with
flame-proof, resilient insulating material (do not make solid).
1
2
3
Mount burner with screws
1
to burner flange.
1
Check setting of electrodes [ch. 9.6].
Fit mixing head [ch. 9.3].