Chapter 9
Maintenance and Service
40001684 Geset 111
Version: 12.05.14
Page 49 of 56
GB
Belt run correction of conveyor belts
Fig. 9-1 Adjust base conveyor principle
No.
Description
1
TRANSPORT DIRECTION
2
DIRECTION WHERE THE BASE CONVEYOR RUNS
3
ADJUSTMENT DIRECTION OF THE DEFLECTION ROLLER TO BELT RUN
CORRECTION
All rolls involved in belt running should be possibly parallel and exactly right-angled to
conveyor axis.
The correction of the belt run should take place at the rolls at which the chain runs from a
longer distance that is not influenced by any deflection.
Requirements
¥
No transportation of products.
¥
Labeler is connected to power.
¥
Labeler was put into operation (refer to chapter “Adjustment and initial
operation“).
Instruction
Please adjust the belt running direction as follows.
Step
Procedure
Risk of injury! The examination of the belt running has to be arranged when
the labeling station is running under load.
- Do not grip in, at or between the moving parts.
1
Start base conveyor.
2
Tense slightly the deflection rollers at the side where the base conveyor runs
to.
3
Transport belts should run for a certain time.
4
Check belt running, correct it again if applicable.