Lync AEGIS
3: INSTALLATION
L-OMM-012_A
•
4/20/2022
Technical Support • (800) 433-5654 • Mon-Fri, 8 am - 5 pm EST
14
of
37
The units should not be positioned in proximity of private offices, bedrooms or areas where low
sound emissions are required. To prevent excessive sound reverberation, do not install the unit in
narrow or confined spaces. For noise levels in specific operating conditions, please see the Aegis
Technical Data Sheet or contact your local Lync rep.
The machine equipped with standard coils should not be installed in a corrosive environment.
Particular care should be taken to avoid atmospheres containing sodium chloride, which can
aggravate corrosion due to galvanic currents; a machine with untreated coils must not, for any
reason, be installed in a marine environment unless provided with the optional coil coating for
coastal areas.
In the case of a marine or highly polluting industrial environment, it is necessary to request coils
with anti-corrosion surface treatment.
If there are any questions about applicability for a particular environment, contact your local Lync
representative.
3.1. Spaces For Installation
The service spaces to comply with are shown on dimensional drawings AP-A-1058, -1059, and -
1060, available at
The evaporating coil must be allowed adequate space for the airflow at both the intake and the
exhaust side
.
In order to prevent poor unit capacity or even interruptions in unit operation it is
absolutely essential to avoid the recirculation of air between the intake and the exhaust
.
High walls near the unit may interfere with its proper functioning
.
Units should be installed a
minimum of 9 feet (3 meters) apart
.
It is advisable to leave sufficient space between the units for removing their larger components
such as the exchangers, compressors or pumps
.
3.2. Anti-Vibration Mounts
In order to reduce vibrations transmitted to the structure, it is recommended to install the machine
on rubber or spring anti-vibration mounts, supplied as an accessory.
The dimensional layout attached to the machine shows the position and load of each antivibration
mount. The anti-vibration mounts must be applied before positioning the machine on the ground.
3.2.1. Rubber Anti-Vibration Mounts
The anti-vibration mount consists of an upper metal bell with a screw to fasten the unit base
.
The
antivibration mount is fastened to the base through the two holes on the flange
.
The anti-vibration
flange bears a number (45,60,70 Shore A) that identifies the hardness of the rubber support
. The
Aegis 250 A has (4) 60° Shore A mounts, the Aegis 350-500 A has (2) 60° and (4) 75° mounts,
and the Aegis W 250-500 have (4) 75° mounts.