Installation step 3
Once the floor has been marked up, the heating
cable can be laid out. Test the cable throughout
installation.
Gently pull the unheated lead from the box.
Do not
remove the spool from the box as this will
cause the heating cable to twist.
After 9 feet of cable has been removed, you will
reach the point at which the unheated lead joins
the heating cable.
The joint should be taped to the floor at the start
point. Ensure that the factory joint lays flat on
the floor. Care should be taken to ensure that the
factory joint remains horizontal, and within the
area to be tiled. The joint should not be bent at
point of entry into the conduit as this may damage
both the factory joint and /or the heating element
within.
The heating cable should be laid in parallel lines
back and forth across the main body of the area to
be heated.
Using the cable spacing markings as tape down
points, secure the heating cable to the floor with
strips of adhesive tape supplied.
19
Tape down end point.