Mobile Generator
General Maintenance
16.11 Storage
Introduction
Extended storage of equipment requires preventive maintenance. Performing
these steps helps to preserve machine components and ensures the machine will
be ready for future use. While not all of these steps necessarily apply to this
machine, the basic procedures remain the same.
When
Prepare your machine for extended storage if it will not be operated for 30 days or
more.
Preparing for
storage
Follow the procedures below to prepare your machine for storage.
■
Complete any needed repairs.
■
Replenish or change oils (engine, exciter, hydraulic, and gearcase) per the
intervals specified in the Scheduled Maintenance table.
■
Grease all fittings and, if applicable, repack bearings.
■
Inspect engine coolant. Replace coolant if it appears cloudy, is more than two
seasons old, or does not meet the average lowest temperature for your area.
■
If your machine has an engine equipped with a fuel valve, start the engine, close
the fuel valve, and run the engine until it stops.
■
Consult the engine owner’s manual for instructions on preparing the engine for
storage.
Stabilizing the
fuel
After completing the procedures listed above, fill the fuel tank completely and add a
high-quality stabilizer to the fuel.
■
Choose a stabilizer that includes cleaning agents and additives designed to
coat/protect the cylinder walls.
■
Make sure the stabilizer you use is compatible with the fuel in your area, fuel
type, grade and temperature range. Do not add extra alcohol to fuels which
already contain it (for example, E10).
■
For engines with diesel fuel, use a stabilizer with a biocide to restrict or prevent
bacteria and fungus growth.
■
Add the correct amount of stabilizer per the manufacturer’s recommendations.
Storing the
machine
Perform these remaining steps to store your machine.
■
Wash the machine and allow it to dry.
■
Move the machine to a clean, dry, secure storage location. Block or chock
wheels to prevent machine movement.
■
Use touch-up paint as needed to protect exposed metal against rust.
■
If the machine has a battery, either remove or disconnect it.
NOTICE:
Allowing the battery to freeze or completely discharge is likely to cause
permanent damage. Periodically charge the battery while the machine is not in
use. In cold climates, store and charge the battery indoors or in a warm location.
■
Cover the machine. Tires and other exposed rubber items should be protected
from the weather. Either cover them or use a readily available protectant.
Summary of Contents for G 25
Page 1: ...5200015081 04 0215 5 2 0 0 0 1 5 0 8 1 Operator s Manual Mobile Generator G 25 T4i G 25 T4f EN...
Page 6: ...Foreword 6 wc_tx003565gb_FM10 fm Notes...
Page 165: ...wc_tx003641gb_FM10 fm 165 G 25 Maintenance Tier 4i Engines Isuzu 770012...
Page 168: ...wc_tx003642gb_FM10 fm 168 Maintenance Tier 4f Engines Isuzu 770006...
Page 169: ...wc_tx003642gb_FM10 fm 169 Maintenance Tier 4f Engines Isuzu 770007...
Page 170: ...wc_tx003642gb_FM10 fm 170 Maintenance Tier 4f Engines Isuzu 770008 770009...
Page 171: ...wc_tx003642gb_FM10 fm 171 Maintenance Tier 4f Engines Isuzu 770010...
Page 191: ...wc_tx003111gb_FM10 fm 191 User s Information for Transport Canada Fuel Tank...
Page 192: ...wc_tx003111gb_FM10 fm 192 User s Information for Transport Canada Fuel Tank...
Page 212: ...Schematics Machines with Deep Sea Controller G 25 212 Notes...
Page 213: ......