14
6 – EQUIPMENT MOUNTING
6.1. Universal blocks mounting
WATER TOPPING-UP
Lead a pipe of the water pipeline to filtration block and connect it to the ingoing
bushing (a thread of 3/8”). Ensure leak resistance of the joint.
ATTENTION!
The system of automatic water filling is designed for water pressure
of 4.5 Bars maximum.
ATTENTION!
After the swimming pool is full with water, adjust the regulating screw of the automatic
water toppin-up device so, that water level will not be lower the upper edge of the skimmer shutter.
CONNECTION OF BLOCK’S FILTRATION COMPARTMENT AND TECHNICAL COMPARTMENT
а
) connection with pump
With the help of pipes d-50mm connect between themselves suction and discharge
openings as it is specified in the “Universal filtration blocks installation scheme”.
Pipes are necessary to lay down so that they will form compensators in order to
prevent pipes damage from temperature expansion. It is necessary to lay down
pipelines in a depth corresponding to a climatic zone of your region.
b) connection with pneumatic button of counter-swimming
(for model VUB20/50)
To avoid damage of pneumatic hose during soil back filling, it is necessary to lead it
in protective pipe of suitable diameter. Lead a pneumatic hose through tightening
gland in the case of block’s technical compartment. Connect pneumatic hose with pneumatic button in
the console of the filtration compartment and pneumatic switch in the control box of the pump in the
technical compartment.
CAUTION!
It is necessary to lay the pneumatic hose smoothly, not bending it!
c) laying of spotlight electric cable
(follow instructions from chapter “General safety rules”)
Lay a protective pipe of suitable diameter between block’s filtration compartment
and technical compartment. Lead in it a copper cable 2
х
2,5mm
2
. One end of a cable
should be in a technical compartment near the spotlight transformer, and the second end near terminals
in filtration compartment. With the help of terminals connect cable wires in the filtration compartment.
Connect terminals between themselves. Push the tube on the connected terminals. Heat the tube by air-
heater (blow-drier) so, that it will crimp tightly the terminals. Connect the second end of cable to
transformer. Tighten cable gland in the technical compartment of filtration block.
d) connection with spotlight pneumatic button
To avoid damage of pneumatic hose during soil back filling, it is necessary to lead it
in protective pipe cover of suitable diameter. Lead a pneumatic hose through
tightening gland in the case of block’s technical compartments. Connect pneumatic
hose with pneumatic button in the console of the filtration compartment and pneumatic switch in the
spotlight transformer.
CAUTION!
It is necessary to lay the pneumatic hose smoothly, not bending it!
e) connection of technical compartment with drainage
With the help of pipes 50mm connect drain outlet of technical compartment with drainage.
Create a slope for pipelines to avoid water level rising inside a technical compartment.
ATTENTION!
If you connect the drainage pipeline to other drainage systems, carry out the
joint so that water from other drainage systems will not get into drainage of the technical
compartment.