Installation & Start-up – HES Series
6
FIGURES 2 and 3 illustrate two methods of lifting & setting Tube-Ice
®
machine on a ice storage bin.
! CAUTION !
The approximate weight of the machine is 1360 pounds.
Always use equipment with adequate load-carrying capacity.
! CAUTION !
FIGURE - 2
Forklift-&-Blocks Method
You need: +
forklift truck with adequate load and height capacities
+
(8) 2X4 wood blocks 8 in. long
+
(2) wooden 2X4’s measuring 3-ft. long
+
pry bar
Step 1.
Position Tube-Ice
®
machine on forks.
! CAUTION !
The Tube-Ice
®
machine may be somewhat top heavy on the rear.
! CAUTION !
Step 2.
Stack wood blocks in each corner of the drip pan on top of the ice storage bin.
Step 3.
Lift and set Tube-Ice
®
machine on wood blocks.
Step 4.
Remove forklift.
Step 5.
Stack 3-ft. long 2X4’s beside drip pan, overlapping front and back of bin.
Step 6.
Using a pry bar with fulcrum on 2X4’s, raise side of machine enough to remove TOP
wood blocks.
! CAUTION !
Do not remove top AND bottom blocks at the same time.
! CAUTION !
Step 7.
Repeat steps 5 and 6 on other side.
Step 8.
With machine sitting on one (1) block under each corner, repeat steps 5, 6, and 7 remove
remaining blocks. Drip pan flanges may bend slightly.
Step 9.
Straighten bent drip pan flanges.
Step 10. Check alignment of ice chute to bin opening.
Summary of Contents for HE S Series
Page 2: ...Installation Start up HES Series 2 Blank Page ...
Page 12: ...Installation Start up HES Series 12 FIGURE 8 Typical Space Diagram ...
Page 26: ...Installation Start up HES Series 26 FIGURE 16 Piping Schematic Air Cooled ...
Page 27: ...Installation Start up HES Series 27 FIGURE 17 Piping Schematic Water Cooled ...