Installation & Start-up – HES Series
23
Refrigerant Connections to Air-Cooled Condenser.
FIGURE - 13
Field Attachment, Air Cooled Condenser Refrigerant Tubing
FOLLOW THESE PROCEDURES TO MAKE A TIGHT JOINT
1.
Solder or braze condenser-tubing ends to the female Rotalock connectors.
2.
Remove dust caps if used, making sure that component plastic seals are intact.
3.
Wipe off connector and spud-threaded surfaces with a clean cloth to prevent the inclusion of
dirt, or any foreign material in the system.
4.
Connector coupling nut should be screwed onto Rotalock spud using the proper amount of
torque (See TABLE-4).
Spud Size
Amount of Torque
1/2” – 5/8”
30-40 FT LBS
7/8”
50-60 FT LBS
1 1/8”
80-100 FT LBS
TABLE – 6
Torque Ratings
1 1/8” IDS X 1 1/4” – 12 Threads
Summary of Contents for HE S Series
Page 2: ...Installation Start up HES Series 2 Blank Page ...
Page 12: ...Installation Start up HES Series 12 FIGURE 8 Typical Space Diagram ...
Page 26: ...Installation Start up HES Series 26 FIGURE 16 Piping Schematic Air Cooled ...
Page 27: ...Installation Start up HES Series 27 FIGURE 17 Piping Schematic Water Cooled ...