VIKING TECHNICAL SUPPORT 1.800.908.0884
1 5
Plans of Installation
GATE OPERATOR INSTALLATION
Positive
Drainage
Electrical
Conduit
Electrical
Junction Box
Top Hinge
Support Box
Load Bearing Hinge
STEP 3
Prepare for Wiring:
Install conduit suited for the application.
Route the conduit to an above ground
junction box.
STEP 5
Instal the Chassis:
a. Ensure the Chassis is level in both
directions and that the Articulation
Point is properly aligned.
!
IMPORTANT:
• USE A LEVEL
• USE A PLUMB BOB
• CHECK TWICE to ensure proper
alignment.
b. Fill the area with concrete and level off
approximately 0.25” below the top of
the Chassis. Before the concrete is fully
cured, check for level and alignment
again.
STEP 4
Prepare for drainage:
Run a flexible drain pipe from the
Gate Operator to an area drain.
Ensure a proper slope and adequate
drainage to prevent any water
accumulation within the motor area.
!
!