1. Filling the heating system
..............................................
7
•
•
•
2. Checking all connections on the heating water side
for leaks
•
3. Switching the power ON
................................................
7
•
4. Matching the control unit to the heating system
........
7
•
5. Checking outputs and actuators
...................................
8
•
6. Adjusting the heating curves
........................................
9
•
•
7. Shutting down the system
............................................. 12
•
•
8. Cleaning the combustion chamber
............................... 12
•
9. Cleaning the flue gas fan and Lambda probe
.............. 13
•
•
10. Emptying the ash pans (if required)
............................. 13
•
•
•
11. Checking the function of safety valves
•
12. Instructing the system user