Routing through a duct
(cont.)
11.
Push on weather collar
7
and secure
safety rope
8
on the lower part.
12.
Only for
balanced
operation: Trim the
last ventilation pipe of the connecting
line so that it reaches to the internal wall
of the duct.
13. Balanced
flue operation: Push on
balanced flue wall bezel
10
and push it
against the duct opening.
Open
flue operation: Push on ventilation
bezel
11
and push it against the duct
opening.
Note
The gap created is designed to provide
secondary ventilation for the duct.
An additional ventilation grille is not
required.
Open
flue operation with combustion air
supply via interconnected rooms:
Push the flue pipe (suitably trimmed
to size) onto the support bend, push
on room interconnection bezel
12
and
secure it on the duct.
17