Notification of readiness for start-up
VITOBLOC 200 BM-190/238
Assembly instructions
31
5780045
GB
Confirmations:
Tested facility complying with latest regulations:
Electrical connection:
We hereby confirm the proper installation of all electrical components for the above project. We
have executed and tested the installation on the basis of applicable norms, VDE directives, and the
requirements of the local power supply company.
Electrical specialist
firm:
Date
Stamp
Signature
It is necessary to register with the EVU for starting up parallel operation.
Electrical supply company
― applying for a power generation system:
yes
no
Date
Name
Signature
Heating connection / gas connection:
We hereby confirm the proper installation of all the gas pipelines for the above project. We have
executed the installation on the basis of applicable norms and directives (e.g., no bending of
expansion joints) and tested it for leaks.
Gas specialist firm:
Date
Stamp
Signature
We hereby confirm the proper installation and testing of the exhaust gas system of the installed
cogeneration module for the above project.
To ensure safety and protect health, the exhaust system has been designed as
overpressure system for load peaks („foreseeable misuse") of up to 4,000 Pa
and tested for suitability and safe use by the master chimney sweeper on the
basis of the state building code.
GPSG (Product Safety Act) Article 4(4)]:
The exhaust gas system complies with DIN V 18160-1 / pressure class H1.
(5,000 Pa gauge pressure / 0.006 l/s m² leak rate)
Specialized
stack construction
firm:
Date
Stamp
Signature