Notification of readiness for start-up
VITOBLOC 200 BM-190/238
Assembly instructions
29
5780045
GB
Mandatory fields, to be completed by customer
:
1. Installation in room
Comments
1.1
All work involving intensive dust and dirt has been completed. The
technical room is clean-swept.
□
yes _________________
1.2
Access and minimum distances as shown in the plant documentation have
been maintained.
□
yes _________________
1.3
The elastic feet are in full contact with the floor and the floor is sufficiently
load-bearing. Clearance between floor and block-type thermal power plant
is approx. 10 cm
(Clearance is not necessary with cogeneration plants larger than 199 kW
electrical)
□
yes _________________
2. Electric installation
Comments
2.1
All electrical components (block-type thermal power plant, valves, pumps,
sensors, etc.) have been installed and connected in accordance with the
applicable VDE guidelines and the requirements of the local power supply
company.
□
yes _________________
2.2
The electric power cables are of the required dimension and were
professionally laid and connected.
Power cable cross section: …………… x ……………. mm²
□
yes _________________
2.3
The integration of the CHP frame into the equipotential bonding is carried
out according to VDE regulations and the regulations of the local supply
company.
□
yes _________________
2.4
The competent power supply company has approved of the injection of the
generated electricity / parallel network operation.
□
yes _________________
Confirmation of the installation specialist Page 3
3. Heating system
Comments
3.1
The heating water connection and the heating water pump are of sufficient
dimension as specified in the documentation.
□
yes _________________
3.2
The hydraulics of the heating system is ready for start-up, i.e., filled with a
thermal carrier medium, pressure tested, bled and integrated in the plant
layout according to our planning and installation instructions.
□
yes _________________
3.3
Considering the block-type thermal power plant output, the consumption of
heat is ensured for at least 2 hours during start-up.
□
yes _________________
4. Ventilation system
Comments
4.1
The ventilation system has been connected in accordance with the
applicable European norms and directives and with our planning and
installation instructions.
□
yes _________________
5. Exhaust gas system
Comments
5.1
The exhaust gas system has been connected in accordance with the
applicable European norms and directives and with our planning and
installation instructions.
(Ensure voltage-free installation of the compensators)
□
yes _________________
5.2
Condensed water drain at a gradient at all low points containing exhaust
gas with water supply (siphon height ≥ 250 mm)
□
yes _________________
5.3
The type of waste gas plant:
□
plastic (with STB)
□
stainless steel
5.4
The manufacturer of the waste gas plant:
________________________
5.5
Number of sound absorbers:
________________________