10
7.
Further line wires No.10,11,15,22,,27,28,45 and 55 are connected to the ionization automatics.
8.
The remaining line wires put through the end piece of the protective tube PG48, and then the actual tube is inserted over the conductors.
9.
Line wire 90, connected to the igniting electrode, is to be inserted through the rubber bushing Ø 13.
10.
Conduit no. 90, connected to the guardian electrode, is to be inserted through the rubber bushing Ø 13.
11.
Conduit no. 92 to burner is to be iserted through bushing PG9.
12.
Cable W1 is to be inserted through the last bushing PG9 and its conduits are to be connected in the distributing box as follows:
Black
J3: 2
Brown
X10: 23
Grey
X10: 24
Blue
X10: 5
Green-yellow
Terminal plate console
13.
The cable W1 opposite end is to be connected to X6 gas valve connection outlet as follows:
Black
X6: L1
Brown
X6: L2
Grey
X6: L3
Blue
X6: N
Green-yellow
PE
14.
The outlet X6 before covering is to be affixed using two self-cutting screws 2,9x19 onto a side piece under the distributing box. Cover it
after its affixing.
15.
Into the X6* gas valve connector are to be connected gas valve Y1 - X8.1 outlet cables.
16.
(small 1
st
step) and X8.2 (High-Low coil) as follows:
X8.1 – Green - Yellow X6*: PE
Blue
X6*: N
Brown
6*: L2
Black
X6*: L1
X8.2 – Green - Yellow X6*: PE
Blue
X6*: N
Brown
X6*: L3
3.1.1
Electrical Panel installation
List of parts needed
1 pc
Power module preconnected
1 pc
End piece of the tube PG 48
1 pc
Nut of the end piece of the tube PG 48
1 pc
End piece of the tube PG 36
1 pc
Nut of the end piece of the tube PG 36
Installation procedure
1.
End pieces of the tubes PG36 and PG48 are to be fastened into the electrical panel console
2.
Wires are to be put through the end piece PG48, and the cover tube secured
3.
Following the connection schematics, instruments are to be connected within the power network module:
BT2 – c.n.. 13,14,18,56
BT1 – c.n. 15,17,18,57
BT4 – c.n. 7,8,58
S1 – c.n. 2,3
H1 – c.n. 40
H2 – c.n. 19.40
H3 – c.n. 29.41
S3 – c.n. 27
S2 – c.n. 24,25
F2 – c.n. 6,7
4.
Green and yellow wire no.59 connect to the electrical panel console
5.
Green-yellow wire no.70 will connect the panel console with the Boiler body
6.
Cable cover tube PG36 should be fastened into end pieces situated on the Distribution Box and the Electrical Panel Console
3.1.2
Completion of the Electrical Installation
List of parts needed
1 pc
Electrical Panel
2 pcs
Blank L&G large
1 pc
L&G small plug with thermomanometer
1 pc
Flexo cable
Installation procedure
1.
The sensing capillary of the instruments are to be inserted into appropriate wells, the manometer sensor then screwed into the return
valve.
2.
The electrical panel is to be mounted on the electrical panel console Insert into the electrical panel opening sequentially: the power
module, two large blanks L & G, and a small blank L & G with a thermo-manometer. Using the bushing PG11, put through the incoming
power cord into the distribution box and connect it to the terminal X10:
Green-yellow
X10: PE
Blue
X10: N
Brown
X10: U
3.
Sockets X8.1 and X8.2 to be connected to the gas valve.
4.
Connector X6* to be connected to X6 socket.