2.4.3 Raised-Floor Installations
If the equipment will be installed on a raised floor, mount it on a pedestal suitably designed to accept the equipment-point
loading. Refer to the base view to design this pedestal.
2.4.4 Removing Shipping Bolts
Cabinets with top-terminal and front-terminal batteries ship with extra bolts installed on the interior doors. Once the cabinet
is in the final position, you can remove the bolts. See Figure 2.1 below, for the shipping-bolt locations.
NOTE: The outer doors are not shown in Figure 2.1 below.
Figure 2.1 Shipping Bolts on Inner Doors
Item
Description
1
Standard-width cabinet
2
Reduced-width cabinet
2 Mechanical Installation
5
Summary of Contents for Liebert
Page 1: ...Liebert Large UPS Battery System Installer User Guide ...
Page 4: ...Vertiv Liebert Large UPS Battery System Installer Guide ii This page intentionally left blank ...
Page 6: ...Vertiv Liebert Large UPS Battery System Installer Guide 2 This page intentionally left blank ...
Page 14: ...Vertiv Liebert Large UPS Battery System Installer Guide 10 This page intentionally left blank ...
Page 39: ...Vertiv Liebert Large UPS Battery System Installer Guide ...