2.8.11. Electrical Installation Inspection
After the electrical installation is completed, confirm the following points as given in the following
.
Table 2-17 Installation Inspection Checklist
Items
Results
The power supply voltage meets the rated voltage on the unit nameplate.
The system electric loop has no open circuit or short circuit.
Power cables and ground cables to the MCBs, indoor unit and outdoor unit are well
connected.
The ratings of the MCBs and fuses are correct.
The control cables are well connected.