Installation
Installation and maintenance instructions ecoTEC plus 0020134833_01
17
4
4.4
Requirements for the installation site
4.4.1 Required minimum clearances/
installation clearances
>
When using accessories, observe the minimum clear-
ances/installation clearances (
¬fig.4.2
).
B
A
C
C
D
4.2
Recommended minimum clearances/installation clearances
Key
A 165 mm (air/flue gas duct
Æ
60/100 mm)
246 mm (air/flue gas duct
Æ
80/125 mm)
B 180 mm
C 5 mm; optimum approx. 50 mm
D 500 mm in front of the boiler to enable easy access for mainte-
nance work (may be provided by an opening door).
Clearance at the side is not required, but the side panels
can also be removed if there is adequate side clearance (at
least approx. 50 mm) in order to facilitate maintenance or
repair work (
¬ section. 4.9
).
It is not necessary to ensure sufficient clearance between
the boiler and combustible materials or components as the
temperature of the boiler will always be less than the maxi-
mum permissible temperature of 85 °C due to its nominal
heat output.
4.4.2 Using installation templates
An installation template is supplied with the boiler to aid
wall mounting.
The template shows the following:
– The position of the fixing holes for the hanging bracket.
– The position of the connections.
– The position of the wall breakthrough of the air/flue gas
duct.
Position the installation template vertically over the instal-
lation site.
>
Attach the template to the wall, using tacks for example.
>
Mark the drill holes for the hanging bracket on the wall.
>
If necessary, mark the position for the wall breakthrough
for the air/flue gas duct.
>
Remove the installation template from the wall.
>
Drill 2 holes
Æ
10 mm for the hanging bracket in the wall.
>
If necessary, cut the wall breakthrough for the air/flue
gas duct.
Summary of Contents for ecoTEC plus VUI
Page 94: ......
Page 95: ......
Page 96: ...0020134833_01 GBIE 072012 Subject to change Manufacturer Supplier 0020134833 ...