7.4 Test
Carry out the following checks once the maintenance
tasks have been completed:
• Start the unit up according to the instructions supplied
with the appliance.
• Check the unit for any signs of escaping gas or water
leaks.
• Check the air/flue duct system for leaks and correct
attachment.
• Check for excess ignition and ensure that the flame
burns regularly and smoothly.
• Check the heating system and hot–water supply for
correct functioning.
• Complete the Benchmark gas boiler commissioning
checklist.