AT LEAST THE 10 FOLLOWING STEPS OF THE
START-UP QUICK GUIDE
MUST BE PERFORMED
DURING THE INSTALLATION AND COMMISSIONING.
IF ANY PROBLEMS OCCUR, PLEASE CONTACT YOUR LOCAL DISTRIBUTOR.
Start-up Quick Guide
1.
Check that the delivery corresponds to your order, see Chapter 3.
2.
Before taking any commissioning actions, read carefully the safety instructions
in Chapter 1.
3.
Before the mechanical installation, check the minimum clearances around the
unit and check the ambient conditions in Chapter 5.
4.
Check the size of the motor cable, DC supply cable, and mains fuses, and check
the cable connections. Read Chapters 6.1.1.1 6.1.1.6.
5.
Follow the installation instructions, see Chapter 6.1.1.8.
6.
The sizes and grounding of control connections are explained in Chapter 6.2.2.
7.
If the Start-Up wizard is active, select the language you want the keypad and the
application to use and confirm by pressing the enter button. If the Start-Up
wizard is not active, follow the instructions in 7a and 7b below.
8.
7a. Select the language of the keypad from Menu M6, page 6.1. Instructions on
using the keypad are given in Chapter 7.
9.
7b. Select the application you want to use from Menu M6, page 6.2. Instructions
on using the keypad are given in Chapter 7.
10.
All parameters have factory default values. To ensure proper operation, check
the rating plate data for the values below and the corresponding parameters of
parameter group G2.1.
•
nominal voltage of the motor
•
nominal frequency of the motor
•
nominal speed of the motor
•
nominal current of the motor
•
motor cos
All parameters are explained in the All in One Application Manual.
11.
Follow the commissioning instructions, see Chapter 8.
12.
The VACON
®
NX Inverter is now ready for use.
Vacon Ltd is not responsible for the use of the inverters against the
instructions.