2. Treatment plant installation
For transport, anchor rods (2 pcs), anchor plates (8 pcs) have been
attached to the sides of the treatment plant. The ventilation pipe is
packed in to the sludge basket.
2.1 Transport, handling and
storage
NOTE! Treatment plants must
be transported and stored in an
upright position
Transfer and sludge pumps have
been attached on supports for
transport and installation. During
commissioning, the pumps are
lowered (section 3.2).
The following items are packed
into the sludge basket inside the
treatment plant during transport:
• chemical
can
•
the lower part of the ventila-
tion pipe
• signal
lamp
• ventilation
pipe
• sludge
bags
•
sludge bag fi xing ring
•
settling test measuring glass
2.2 Planning and choice of
treatment plant location
A plan is required for wastewater
system construction. It is
worthwhile to contact the designer
at an early stage,since the plan
must be presented as part of the
permit application when building or
renewing a wastewater system.
Planning requires competence
and it is best left to water service
experts who will carry out the
necessary analyses on-site. The
requirements for plan contents
are stated in the Wastewater Act.
When starting to plan, it is impor-
tant to fi nd out any municipality
environmental protection regula-
tions.
In addition to wastewater legisla-
tion, regional requirements can be
a signifi cant factor in aff ecting the
planning.
7