EcoFoot5DTM is a 5-degree ballasted racking system designed to fi t more modules on a roof, maximizing power density. The modular de-
sign is built on the proven, industry-preferred, beautifully simple and fast-to-install modular technology of the EcoFoot platform and sister
product, E.
EcoFoot5D consists of fi ve simple components. Installation is accomplished in six simple steps. Much of the installation is tool-less.
EcoFoot5D Bases self-align, requiring only two chalk lines. The PV module installation automatically moves the Bases into perfect place-
ment. Inter-row ballast placement and easy-reach wire management provide superior accessibility during and after installation.
Stackable Bases enable the transport of up to 290kW of Bases on 1 standard pallet, streamlining logistics. The combined effect of simplic-
ity, maximum density, and minimized shipping, storage and transporting costs results in an ultra cost-effective racking solution.
FIELD SUPPORT CONTACT INFORMATION
Unirac proudly offers dedicated engineering expertise and superior customer support. For questions about the installation procedures or a
specifi c application, please visit www.unirac.com.
INSTALLER RESPONSIBILITY
The installer is solely responsible for:
•
Utilizing all necessary safety equipment, as required by applicable rules and regulations.
• Complying with all applicable local and national building codes, including any that may supersede this manual.
•
Ensuring that Unirac® EcoFoot5D™ and other products are appropriate for the specifi c installation and are designed for the installa-
tion environment.
• Ensuring that the roof, its rafters, connections, and other structural support members can support the array under all conditions.
•
Maintaining the waterproof integrity of the roof including selection of appropriate fl ashing if the system is being installed using at-
tachments.