INSTALLATION GUIDE
PAGE
HIGH DENSITY 5-DEGREE
BALLAST RACKING SYSTEM
8
SYSTEM INSTALLATION STEPS
Step 1 – Install Pre-assembled Universal Clamps into Bases
• Place Lower and Upper Universal Clamp into EcoFoot5D Base as shown.
• Push Clevis Pins completely into EcoFoot5D Base to secure Rocker.
Step 2 – Position Array
• Snap two chalk lines on roof denoting outside edges of the EcoFoot5D
Bases, per project drawing. Start from the north or south edge. Ensure
chalk lines are square.
• Place EcoFoot5D Bases in approximate position throughout the array.
Installation Tips
• Only install Clamps where modules will rest.
• See Step 3 for correct placement and orientation of Clamps.
Installation Tips
• As you build the array, panels will space the Bases. Roughly place a few
rows of Bases at a time so
that they are within reach of fi nal location.
Note: The Upper Clamp includes a post and nut to install the Wind
Defl ector as shown in Step 6.