PART II: INSTALLATION
14
2.0 MOUNTING AND CONNECTING THE BURNER
2.2 Handling the burner
The burner is mounted on a stirrup provided for handling the burner by means of a fork lift truck: the forks must be inserted into the A
anb B ways. Remove the stirrup only once the burner is installed to the boiler.
The burner is provided with eyebolts, for handling operations.
2.3 Fitting the burner to the boiler
To perform the installation, proceed as follows:
1
drill the furnace plateas decribed in paragraph (“Overall dimensions”);
2
place the burner towards the furnace plate: lift and move the burner by means of its eyebolts placed on the top side (see”Lifting and
moving the burner”);
3
screw the stud bolts (5) in the plate holes, according to the burner’s drilling plate described on paragraph “Overall dimensions”;
4
place the ceramic fibre plait on the burner flange;
5
install the burner into the boiler;
6
fix the burner to the stud bolts, by means of the fixing nuts, according to the picture below.
7
After fitting the burner to the boiler, ensure that the gap between the blast tube and the refractory lining is sealed with appropriate
insulating material (ceramic fibre cord or refractory cement).
2.1 Packing
The burners are despatched in wooden crates whose dimensions are:
2280 x 1730 x 1360 (L x P x H)
Packing cases of this type are affected by humidity and are not suitable for stacking.
The following are placed in each packing case:
z
burner with detached gas train;
z
gasket or ceramic fibre plait (according to burner type) to be inserted between the burner
and the boiler;
z
envelope containing this manual and other documents.
To get rid of the burner’s packing, follow the procedures laid down by current laws on disposal
of materials.
ATTENTION! The handling operations must be carried out by specialised and trained personnel. If these opera-
tions are not carried out correctly, the residual risk for the burner to overturn and fall down still persists.
To move the burner, use means suitable to support its weight (see paragraph “Technical specifications”).
The unpacked burner must be lifted and moved only by means of a fork lift truck.
PART II: INSTALLATION
H
P
L
A
B
Eyebolts
Eyebolts