PART III: OPERATION
30
12 Ensure the pressure entering the main valves is not excessive due to damage to or wrong adjustment of the line pressure regulator
13 Ensure the gas supply minimum pressure is at least equal to the pressure required by the pressure curves - burnt gas flow
Adjustments - brief description
The air and fuel rates adjustments must be performed at the maximum ouptput first (“high flame”): see the LMV5.. related manual..
Check that the combustion parameters are in the suggested limits.
Check the flow rate measuring it on the counter or, if it was not possible, verifying the combustion head pressure by means of a dif-
ferential pressure gauge, as described on par. “Measuring the gas pressure in the combustion head”.
Then, adjust the combustion values by setting the “gas/air” ratio” curvepoints (see the LMV5.. related manual).
Set, now, the low flame output, in order to avoid the low flame output increasing too much or that the flues temperature gets too low
to cause condensation in the chimney.
Start-up procedure
1
Turn the burner on.
2
the LMV control box starts the system test cycle: the AZL display shows the
System Test
message; at the end of the test, it shows
the main page and the system stops (the safety chain is open) waiting for the startup enabling signal (standby - Program phase no.
12)
Main page
3
check the fan motor rotation (see related paragraph).
4
make the safety chain enabling the system to start up
5
the combustion cycle starts: the system will show the operating stages
- Prepurging
(program phase no.30)
- Driving to ignition position
(program phase no.36)
- Ignition position
(program phase no.38)
- Fuel
(the fuel solenoid valves open)
- Flame
(the flame lights up)
- Driving to low flame
(the actuator drives to low flame).
NOTE:
the
C
and
A
, on the .
Once the ignition cycle ends, the main page is shown:
Main page
Set point:
temperature set-point
Act value:
actual temperature value
Load:
load percentage (burner output)
Flame:
percentage of flame detection current.
By pressing the ENTER key the display shows the second page:
DANGER! Venting the air from the piping must take place in safe conditions, avoiding dangerous concentrations
of fuel in the rooms. You must therefore ventilate the rooms and wait long enough for the gases to dissipate out-
side before switching on.
To ensure the proper operation of the flow sensors, the fuel/air pipes must be free of liquid residues such as oil
or water. Also, make sure that the silencer is installed on the air intake.
Setpoint
80°C
Act.value
78°C
Fuel
GAS
Standby
12
Setpoint
80°C
Act.value
78°C
Load
24%
Flame
60%
Summary of Contents for H365X
Page 46: ......
Page 47: ......
Page 49: ...Siemens LMV5x Service Manual M12920CC rev 2 1 08 2017...
Page 56: ...8...
Page 60: ...12 2 2 LMV5x program structure...
Page 87: ...39...
Page 94: ......
Page 95: ......
Page 96: ...Note Specifications and data subject to change Errors and omissions excepted...
Page 98: ...Annex1 Example for motor cable...
Page 99: ......
Page 100: ...Annex 2 Example for sensor cable...
Page 101: ......
Page 102: ......
Page 106: ......