PART IV: OPERATION

31

Manifacturer level (OEM)

PHASES LIST

During operation, the following program phases are shown. The meaning for each phase is quoted in the table below

Entering the Parameter levels

By means of a proper use of the keys, it is possible to enter the various level parameters, as shown in the following flow chart:

The burner and consequently the LMV2x.. are factory set; the air and fuel curves as set as well.

Fase /

Funzione

Function 

Ph00 Fase 

blocco

Lockout 

phase 

Ph01 

Fase di sicurezza

Safety phase 

Ph10 

t10 = tempo raggiungimento posizione riposo

t10 = home run 

Ph12 Pausa

Standby 

(stationary) 

Ph22 

t22 = tempo di salita ventilatore (motore ventilatore  = ON, valvola intercetta-
zione di sicurezza = ON)  

t22 = fan ramp up time (fan motor = ON, 
safety shutoff valve = ON) 

Ph24 

Verso posizione preventilazione

Traveling to the prepurge position 

Ph30 

t1 = tempo preventilazione

t1 = prepurge time

Ph36 

Verso posizione accensione

Traveling to the ignition position 

Ph38 

t3 = tempo preaccensione

t3 = preignition time 

Ph40 

TSA1 = primo tempo sicurezza (trasformatore accensione ON)TSA1 = primo 
tempo sicurezza (trasformatore accensione ON)

TSA1= 1st safety time (ignition transformer 
ON) 

Ph42 

TSA1 = primo tempo sicurezza (trasformatore accensione OFF)

TSA1 = 1st safety time (ignition transformer 
OFF)
t42 = preignition time OFF 

Ph44 

t44 = intervallo 1

t44 = interval 1 

Ph50 

TSA2 = secondo tempo sicurezza

TSA2 = 2nd safety time 

Ph52 

t52 = intervallo 2 

t52 = interval 2 

Ph60 

Funzionamento 1 (stazionario) 

Operation 1 (stationary) 

Ph62 

t62 = massimo tempo bassa fiamma (funzionamento 2, in preparazione per 
spegnimento, verso bassa fiamma)

t62 = max. time low-fire (operation 2, prepa-
ring for shutdown, traveling to low-fire) 

Ph70 

t13 = tempo postcombustione 

t13 = afterburn time 

Ph72 

Verso posizione postcombustione

Traveling to the postpurge position 

Ph74 

t8 = tempo postventilazione

t8 = postpurge time 

Ph80 

t80 = tempo evacuazione controllo tenuta valvole

t80 = valve proving test evacuation time 

Ph81 

t81 = tempo perdita pressione atmosferica, prova  atmosferica

t81 = leakage time test time atmospheric  
pressure, atmospheric test 

Ph82 

t82 = test perdita, test riempimento

t82 = leakage test filling test, filling 

Ph83 

t83 = tempo perdita pressione gas, test pressione

t83 = leakage test time gas pressure, pres 
sure test 

Ph90 

Tempo attesa “mancanza gas”

Gas shortage waiting time 

 

 

 

2

1

3

4

5

6

1
2
3

4
5
6

Summary of Contents for C70N US

Page 1: ...M039682WA 0 0 01 2023 BURNERS BRUCIATORI BRULERS BRENNER QUEMADORES MANUAL OF INSTALLATION USE MAINTENANCE Microprocessor controlled C70N US LMV 2x 3x Gas burners Premix...

Page 2: ...non original components whether spare parts kits accessories and optionals Force majeure Furthermore the manufacturer declines all responsibility for non compliance with this manual Personnel training...

Page 3: ...rner shut down reser the control box by means of the RESET pushbutton If a second shut down takes place call the Tech nical Service without trying to RESET further The unit shall be operated and servi...

Page 4: ...UNI EN ISO 12100 2010 Safety of machinery General principles for design Risk assessment and risk reduction For the following information please refer to the data plate Burner type and burner model mu...

Page 5: ...trodes and a high voltage transformer a pilot flame may also be employed depending on burner configuration Pre ventilation of the combustion chamber is usually implemented according to gas directives...

Page 6: ...es gas proving system 8 2 gas valves gas proving system maximum gas pressure switch 8 GAS CONNECTION 32 1 1 4 NPT 40 1 1 2 NPT 50 2 NPT 65 2 1 2 NPT 9 MICRO PROCESSOR CONTROL EA micro processor contro...

Page 7: ...ge of the machine To get the input in kcal h multiply value in kW by 860 Data are referred to standard conditions atmospheric pressure at 1013mbar ambient temperature at 15 C Back pressurembar mbar C7...

Page 8: ...nt type of fuel please refer to the paragraph Fuel at the beginning of this chapter GAS PRESSURE IN Potenza kW Curves are referred to pressure 0 mbar in the combustion chamber Gas pressure in combusti...

Page 9: ...imensions mm C70N 87 981 1970 1020 545 P 305 4 5 3 320 320 12 M 28 338 338 P 204 400 239 10 15 590 376 400 350 302 637 345 342 200 345 302 P 295 190 238 405 burner flange Boiler recommended drilling t...

Page 10: ...ns ATTENTION Before executing the connections to the gas pipe network be sure that the manual cutoff valves are closed PS PSH PSL PSL PSH PS M M MB DLE VGD MBE gas inlet gas inlet gas inlet Legend 1 F...

Page 11: ...water steam Burner input Backpressure in the combustion chamber Dimensions of the combustion chamber inclu ded the reverse smoke chamber NOx emissions requested Choosing the burner To clearly explain...

Page 12: ...uitable for the application for which it is intended To correctly match the burner to the boiler Check that the required power and the pressure in the combustion chamber are within the working range A...

Page 13: ...g the burner The burner is designed to work positioned according to the picture below For different installations please contact the Manufacture WARNING before executing the connections to the gas pip...

Page 14: ...ed with a hydraulic lift or a small manual crane A The burner is mounted on a stirrup provided for handling the burner by means of a fork lift truck the forks must be inserted into the A anb B ways Re...

Page 15: ...ry connections and checks having been made 1 0 2 3 4 A A PHASE 1 Position the head and secure it with the nuts NB Position the head according to the reference given by the pin on the flange PHASE 2 In...

Page 16: ...g section 4 fix the burner flange with nuts 2 3 to the studs 4 of the boiler according to the picture After fitting the burner to the boiler ensure that the gap between the blast tube and the refracto...

Page 17: ...ording to the procedure set by laws in force CAUTION The direction of gas flow must follow the arrow on the body of the components mounted on the gas ramp valves filters gaskets NOTE the bellows unit...

Page 18: ...tube lines use appropriate sealing agent 2 Insert MB DLE note position of O rings 3 Remove MultiBloc between the threaded flanges 4 After installation perform leakage and functional test 5 Disassembl...

Page 19: ...s pressure switch 4 PGMAX maximum gas pressure switch 5 Actuator with integrated pressure stabiliser 6 On Off actuator 7 Valve body Threaded 8 Valve body Flange On equipment versions Facile VD R must...

Page 20: ...ens VGD VRD SKPx5 Auxiliary optional micro switch Gas valve If the auxiliary microswitch POC is required a dedicated actuator different from the one usually supplied must be ordered The con nection is...

Page 21: ...21 Siemens VGD Pressure taps G 1 4 G 1 8 G 1 4 G 3 4 G 1 8 G 1 4 G 1 8 Strainer 1 9 3 4 5 2 11 7 6 8 2 V 1 V 10 1 2 4 3 9 1 6 10 3 2 11 10 5 6 7 8 9 Legend pi Inlet pressure pm Pressure between valve...

Page 22: ...have in the implant there must be Have earthing connected to the burner always check the connection functionality and health and safety compliance of the earthing cable beforehand If in doubt request...

Page 23: ...lete with a terminal strip for the connection to the system electrical line and in case of on board control panel a plug for the connection to the modulation probe if any QF B QF A BURNER SUPPLY TERMI...

Page 24: ...ENTION the burners are supplied for three phase 380 400 415 480 V supply and in the case of three phase 220 230 240 V supply it is necessary to modify the electrical connections into the terminal box...

Page 25: ...PART III INSTALLATION 25 Probe connection with 7 pins connector Trasducer passive connection only...

Page 26: ...with fan motor driven by inverter in addition to the air and fuel adjustment curves also have a fan motor speed adjustment curve Generally the curve of the inverter goes from 50 to 100 of the engine...

Page 27: ...on the release button In the event of a lockout the cause must be evaluated if the flame back warning light is on before unlocking the control box it is mandatory to check the integrity and good cond...

Page 28: ...ves the air damper to the maximum opening position then the fan motor starts up the pre purge phase begins During the pre purge phase the air damper complete opening is signalled by the light B2 on se...

Page 29: ...seriously damage valves and pressure regulator 10 Check the sense of rotation of the electrical motors 11 Bleed the line getting rid of all the air in the pipe as far as the main gas valve 12 Ensure...

Page 30: ...equest 5 Oil pre heater energised 6 Fan motor energised 7 Ignition transformers energised 8 Open valves 9 Flame 10 Lock unlock codes 11 Closing actuator 12 Opening actuator 13 Unit measure 14 Key F A...

Page 31: ...TSA1 primo tempo sicurezza trasformatore accensione ON TSA1 1st safety time ignition transformer ON Ph42 TSA1 primo tempo sicurezza trasformatore accensione OFF TSA1 1st safety time ignition transform...

Page 32: ...me basic parameters as 5 Example choose parameter 102 to show the date the display shows parameter 102 flashing on the left and characters _ _ on the right 6 press InFo for 1 3 seconds the date will a...

Page 33: ...and find out the fault in the Error table To perform the reset press InFo for one second The unit displays an event which does not lead to shutdown The display shows current error code c alternating w...

Page 34: ...ameter list 2 Once the last parameter is accessed 143 by pressing the End message will blink 3 PressPress InFo for more than three seconds or for more than three seconds orto return to the normal disp...

Page 35: ...n reduces start flow rate anticlockwise rotation increases it Do not use a screwdriver on the screw VR The pressure stabilizer is adjusted by operating the screw VS located under the cover C By screwi...

Page 36: ...essure port of the minimum gas pressure switch Slowly close the manual cutoff valve placed upstream the pressure switch see gas train installation diagram until the detected pressure is reduced by 50...

Page 37: ...n and examine the gas filter cartridge and replace it if necesssary Remove and clean the combustion head Examine and clean the ignition electrodes adjust and replace them if necessary Examine and clea...

Page 38: ...twice as high compared to the last check You can change the filter without removing the fitting 1 Interrupt the gas supply closing the on off valve 2 Remove screws 1 4 using the Allen key n 3 and rem...

Page 39: ...to push 1 2 3 4 5 6 7 1 Position VD on VB fig 2 3 2 Slide VD forward up to the stop fig 4 3 Screw VD on with 2 M5 screws for each max 5 Nm 44 in lb fig 5 6 4 VD can be mounted rotated by 180 fig 7 VB...

Page 40: ...ring the electrode to the holder 4 5 Clean the electrode sensing element 6 Reinsert the entire electrode assembly following previous steps in reverse ATTENTION avoid the ignition and detection electro...

Page 41: ...o stop the burner in the seasonal stop proceed as follows 1 turn the burner main switch to 0 Off position 2 disconnect the power mains 3 close the fuel valve of the supply line Burner disposal In case...

Page 42: ...itch functions and links Burner control damaged Replace burner control BURNER LOCKS OUT WITHOUT ANY GAS FLOW Gas valves don t open Check voltage on valves if necessary replace valve or the burner cont...

Page 43: ......

Page 44: ...a L Galvani 9 35011 Campodarsego PD ITALY Tel 39 049 9200944 Fax 39 049 9200945 9201269 web site www cibunigas it e mail cibunigas cibunigas it Note specifications and data subject to change Errors an...

Reviews: