Evaluation Unit 

The evaluation unit is built into a poly-carbonate housing (IP65). The electrical connections to the 
power supply, reference potential, sensor electrodes and relay contacts are established via three 
cable connections. 

 

Figure 1 

 

2.1

 

Electrical Connections 

Con-
nector 

Pin  Connection 

X1 

24 V

AC/DC

  Supply Voltage 

Both polarity accepted 

 

 

PE 

Reference Potential 

Connected to the earth 

X2 

Relay common contact 

 

NO 

Relay normally open contact 

 

NC 

Relay normally closed contact 

X3 

Core 

Connected to the measuring electrode. 

Use coaxial cable (75Ω) 

 

Shield 

Connected to the opposite electrode 

By inductive load connected on X2 (relay output), use spike suppression to prevent damage of the 
relay contacts. 

Summary of Contents for S-SW-8

Page 1: ...manual adjustment switch SW2 2 to OFF 6 2 4 2 Sensitivity setting relay switching point 6 2 5 Technical Data 7 3 Montage Cabling 8 3 1 System arrangement 8 3 2 Electrical connections 9 4 Installation...

Page 2: ...the sensitivity is set appropriately the presence of the new objects is detected A potential free contact relay turns ON OFF according to the IN OUT movement of objects over the sensing area the swit...

Page 3: ...Connections Con nector Pin Connection X1 1 24 VAC DC Supply Voltage Both polarity accepted 2 3 PE Reference Potential Connected to the earth X2 1 C Relay common contact 2 NO Relay normally open contac...

Page 4: ...of the evaluation unit via the shield of the coaxial cable Montage structure C The design of the mounting structure depends on the conditions at the installation place It must be made of conductive ma...

Page 5: ...switch on point occupied and the switch off point free for the relay The sensor signal level for the switch ON point is stronger than the switch OFF point A larger hysteresis means that the switch ON...

Page 6: ...ves the reference value of the system The sensor electrodes must be free when performing a new adjustment No objects or person may be near the sensor electrodes SW2 2 OFF Memory OFF After power ON the...

Page 7: ...n 2 5 Technical Data Parameter Sim Condition min tip max Unit Supply Voltage UV AC DC 18 24 30 V Operation Power IV 18V UV 30V 3 W Environment Tempera ture TF In operation 15 20 55 C TL Storage 20 60...

Page 8: ...ts to be detected This ensures safe switching behavior The evaluation unit should be installed near the sensor electrodes The sensor line coaxial cable between the evaluation unit and sensor electrode...

Page 9: ...e 5 Connect the reference potential of the evaluation unit X1 3 direct to the earthed mounting struc ture 6 Connect the supply voltage 24VAC DC to the evaluation unit X1 1 X1 2 7 First operation By th...

Page 10: ...timum sensitivity for the working object is set LED2 confirms the process by flashing briefly 2 Manual Relay OFF LED5 OFF Rotate the switch SW1 clock wise until the relay switches ON plus three more p...