RDU Mk2 Installation & Programming Manual
Document No: LT0499
Alignment, Adjustment & Placing Into Operation
Page 9-8
8 April 2015
Issue 1.02
9.2.5
COMMISSIONING CHECKLIST: SLIMLINE RDU
The following checklist should have been completed and supplied by the manufacturer. It
should be placed with other System Configuration Information. Commissioning staff should
check the installed RDU against it. (Note that all PCBs are electronically tested and
adjusted before being fitted to the RDU).
1.
CABINET & GENERAL
A)
Cabinet colour
– Grey Gloss PR12/816C
- Other: ______________________________________
B)
Cabinet undamaged (Paint OK)
C)
Door aligned correctly
D)
Cabinet Door locks firmly, operates microswitch
E)
Lock - 003 Type & two keys supplied
F)
Display, Keypad and Status LEDs fitted & aligned correctly
G)
Operator Manual included
H)
VIGILANT
TM
RDU label completed
2.
PCBS & WIRING
A)
Controller/Display fitted securely
B)
Remote Termination Bd fitted securely, Fuse F1 installed
C)
FRC Looms fitted correctly
D)
Door switch fitted to J7 of Remote Termination Bd