Commissioning
Function tests
Hans Turck GmbH & Co. KG | T +49 208 4952-0 | [email protected] | www.turck.com
V01.00 | 2022/09 | 15
7.2
Safety planning
The operator is responsible for the safety planning.
Prerequisites
Perform a hazard and risk analysis.
Develop a safety concept for the machine or plant.
Calculate the safety integrity for the complete machine or plant.
Validate the complete system.
7.3
Safe commissioning
7.3.1
Installing connecting cables safely
NOTICE
Incorrect connection of connecting cables
Danger of cross connections
Install and connect the cables safely and separately in accordance with
EN 60204-1.
Install cables with cross-circuit protection if the safe installation of the cables is
not possible.
7.3.2
Switch off supply voltage safely
WARNING
1-pole switch-off the supply voltage
Safe separation not guaranteed
Always switch-off the supply voltage on both poles.
7.3.3
Connecting sensors and actuators
WARNING
External feed
Deactivation of the galvanic isolation
If the galvanic isolation is used, ensure on the application side that no external
feed can occur.
DXP channels that operate with safe disconnectable potential must be supplied
by the corresponding conenctor.
7.4
Function tests
Have the function test carried out by qualified personnel only.
Before commissioning the system, check and document the switch-off of the V1 and V2
voltage group by an upstream safety relay.
Control the switching behavior of he output circuits.