11
RLC-SVX023B-GB
Installation - Mechanical
Water Drainage
Locate the unit near a large capacity drain for water vessel drain-down during shutdown or repair. Condenser and
evaporator water pipes are provided with drain connections. Refer to “Water Piping.” All local and national codes apply.
Access Restrictions
Refer to the unit submittals for specifi c dimensional information (documents supplied in document package coming
with unit).
Handling Procedure
Follow instructions given in the lifting and handling document supplied with documentation package shipped with
the unit.
Figure 1 –
Handling
YES
NO
930
1042
Isolation Pads
1.
The elastomeric pads shipped (as standard) are adequate for most installations. For additional details on
isolation practices, consult an acoustical engineer for sensitive installations. It is possible that some vibration
frequencies can be transmitted into the foundations. This depends on the building structure. It is recommended
for these situations to use neoprene isolators instead of elastomeric pads.
Drawings to locate isolation pads are supplied with unit document package.
2. During
fi nal positioning of the unit, place the isolation pads as indicated in submittal drawings. Level the unit.
Drawings to locate isolation pads are included with in document package sent with the unit.