background image

 

Page 17

Installer’s Guide

Gas Pressure Set-up Precautions

IMPORTANT:  

Do not connect gas piping to the unit until a line 

pressure test has been completed. This unit should never be 

exposed to gas line pressure in excess of 14 inches water column 

(1/2 PSIG). The furnace and its equipment shutoff valve must be 

disconnected from the gas supply piping system during any pres-
sure testing of that system at test pressures in excess of 1/2 psi. 

The furnace must be isolated from the gas supply piping system 

by closing its individual manual shut-off valve during any pressure 

testing of the gas supply piping system at test pressures less than 

or equal to 1/2 psig (3.48 kPa).

Gas Supply Line Pressure

Before connecting the unit to the gas supply line, be sure to deter-

mine the gas pressure in the line.

If the gas supply pressure is excessive (above 14 inches water 

column or 1/2 psig), install a pressure regulator either at the supply 

source or in the branch circuit serving the unit.  Once the regulator 

is installed, set it to provide a pressure of 7 inches water column 

with the unit operating and no greater than 14 inches water column 

with the unit not operating.

NOTE:

 Gas pressure in excess of 14 inches water column 

(1/2  psig) may damage the regulator, while improper regulation 

may result at pressures lower than 5.5 inches water column at 

the unit inlet.

If the supply line pressure is below the minimum supply pressure 

indicated on the unit nameplate, contact the gas supply company.

Follow these steps to complete the installation of the unit gas pip-

ing.  See Figure 17.

NOTE:

  The shut-off gas cock must be installed outside of the 

unit and should meet the specifications of all applicable national 

and local codes

.

Table 2. Natural Gas Only

TABLE OF CUBIC FEET PER HOUR OF GAS

FOR VARIOUS PIPE SIZES AND LENGTHS

PIPE

SIZE

(inch)

LENGTH OF PIPE (feet)

10

20

30

40

50

60

70

1/2

132

92

73

63

56

50

46

3/4

278

190

152

130

115

105

96

1

520

350

285

245

215

195

180

1-1/4

1050

730

590

520

440

400

370

  THIS TABLE IS BASED ON PRESSURE DROP OF 0.3 INCH W.C. AND 0.6 SP.GR. GAS

IMPORTANT

:

  

Before making the gas pipe connection give serious 

consideration to providing the clearance necessary to remove the 
access panels on the unit (e.g., economizer and filter access panels).

NOTE

: In the absence of local codes, the installation must con-

form with American National Standard--Z223.1--National Fuel 

Gas Code, Latest Revision.

The available gas supply must agree with the required gas supply 
marked on the unit nameplate.  Minimum permissible gas supply 
pressure for purpose of 

input adjustment

 must be at least 7.0 in. w. 

c. (inches water column) for natural gas and 11 in. w. c. for LP Gas.

Pipe Delivery Schedule

NOTE:

  The following procedure and tables apply to Natural 

Gas 

only.

  1. Obtain from the gas company the heating value and specific 

gravity of the gas delivered.

  2. Determine the exact length of pipe needed.

  3. Read BTUH input nameplate on the furnace.

  4. Use the multiplier opposite the specific gravity of the gas given 

in Table 1 below and insert in the following formula:

  5. Using Table 2, select the pipe length nearest to calculated size.

  6.  Follow this line vertically down to the exact CFH found in Step 4 

above or the next highest value.

  7. Read horizontally to the left of this column for the required pipe 

size diameter.

Table 1

. Specific Gravity Multiplier

DEALER INSTALLED

GROUND UNION

1/8" N.P.T.PLUGGED

ACCESS FOR TEST

GAUGE CONNECTION

FROM

GAS SUPPLY

FIELD SUPPLIED MAIN

GAS VALVE, MUST BE

INSTALLED BY DEALER

OUTSIDE OF UNIT.

UNIT

TO MAIN

CONTROL

VALVE

6"

MIN

DRIP LEG
(6" MIN)

Figure 17. Gas Pipe

NOTE:

  If this is an LP Gas application, consult your LP Gas 

supplier for pipe sizes and deliveries.

Furnace Input in BTUH

Gas Heat Contne in BTU/Cu. Ft. X Multiplier

CFH =

  1. Install a tapped, Style A (1/8-inch NPT tap) shut-off gas cock at 

the end of the gas supply line near the unit.  Be sure the tapped 
gas cock is downstream of the pressure regulator, if used.

  2. Install a ground union joint downstream of the shut-off cock.  

This joint must also be installed outside of the unit.

  3.  Install a drip leg at least six (6) inches in depth next to the union 

as shown in Figure 17.  This drip leg is required to collect any 
sediment that may be deposited in the line.

SPECIFIC 

GRAVITY

MULTIPLIER

MULTIPLIERS TO BE USED 

WHEN THE SPECIFIC GRAV-

ITY OF THE GAS IS OTHER 

THAN 0.60

.50

1.10

.55

1.04

.60

1.00

.65

.962

Summary of Contents for 4DCZ6036

Page 1: ...erent hazards during installation and service the electrical supply must be disconnected and the main gas valve must be turned off If operating checks must be performed with the unit operating it is t...

Page 2: ...ingpressureexceedsthelimitofR 22 Proper service equipment is required Failure to use proper service tools may result in equipment damage or personal injury SERVICE Use only R 410A Refrigerant and appr...

Page 3: ...arefully before attempting to install oper ate or perform maintenance on this unit Installation and maintenance should be performed by qualified service techni cians only This unit is listed by Underw...

Page 4: ...Guide Step 2 Determine Unit Clearances Figure 1 4DCZ6036 1 of 3 Figures 1 through 6 show the unit critical dimensions NOTE The view labeled Bottom Side represents the Base as viewed looking up from u...

Page 5: ...Page 5 Installer s Guide Figure 2 4DCZ6036 2 of 3...

Page 6: ...Page 6 Installer s Guide Figure 3 4DCZ6036 3 of 3...

Page 7: ...Page 7 Installer s Guide Figure 4 4DCZ6048 through 4DCZ6060 1 of 3...

Page 8: ...Page 8 Installer s Guide Figure 5 4DCZ6048 through 4DCZ6060 2 of 3...

Page 9: ...Page 9 Installer s Guide Figure 6 4DCZ6048 through 4DCZ6060 3 of 3...

Page 10: ...fer to the Installation section for instruction on converting the supply and return airflow covers to down airflow 3 The field assembled Roof Mounting Curb BAYCURB050A or BAYCURB051A or a field fabric...

Page 11: ...clearance to combustible mate rial shall be maintained on air outlet duct Rooftop Installation Curb Mounting Convert Horizontal Airflow to Down Airflow The factory ships the unit for horizontal airflo...

Page 12: ...he unit by attaching clevis hooks pins or bolts to the unit casing casing hardware corner lugs angles tabs or flanges Failure to observe these warnings may result in equipment damage 1 Before preparin...

Page 13: ...r roof top applications using field fabricated ducts and sleeper rails rather than a curb or frame use the following procedure 1 Locate and secure the sleeper rails to the roof Three 3 sleeper rails a...

Page 14: ...drawing The manufacturer is not responsible for the unauthorized use of this drawing and expressly disclaims any liability for damages resulting from such unauthorized use Gasket Seal Spreader Bars B...

Page 15: ...rizontal Airflow Application with Frame Supply Air Return Air Roof Flashing Channel Iron Center Support Center Sup port required on all Frame Applications Angle Iron Frame Roof Flashing Return Air Ang...

Page 16: ...ise and vibration transmission Elbows with turning vanes or splitters are recommended to minimize air noise and resistance The first elbow in the ductwork leaving the unit should be no closer than two...

Page 17: ...making the gas pipe connection give serious consideration to providing the clearance necessary to remove the accesspanelsontheunit e g economizerandfilteraccesspanels NOTE In the absence of local cod...

Page 18: ...chonthegasvalveinletboss connect the gas piping to the unit Check the completed piping for leaks using a soap and water solution or the equivalent 6 After installation of the gas pipe in the unit the...

Page 19: ...Models that require 49 orifices for altitudes from 7000 8000 orifices must be changed to 50 HIGH ALTITUDE DERATE CHART NAT Altitude In Feet Inputs shown are with factory orifices 3 5 WC High Fire 1 8...

Page 20: ...ed A brief explanation of each mode follows RESTRICTED In the restricted mode of operation an outdoor temperature sensor is used to cause the unit to operate in the heat pump mode above a selected out...

Page 21: ...ns IMPORTANT Upon completion of wiring check all electrical connections including factory wiring within the unit Make sure all connections are tight Replace and secure all electrical box covers and ac...

Page 22: ...Page 22 Installer s Guide Figure 22 4DCZ6 Field Wiring Diagram 4DCZ6 FIELD WIRING DIAGRAM Y2 YL RD 2NDSTAGECOMPRESSOR 1STSTAGECOMPRESSOR CONSTANTCIRCULATION...

Page 23: ...h the compressor operating check the line voltage at the unit The voltage should be within the range shown on the unit nameplate If low voltage is encountered check the size and Step 5 Unit Startup le...

Page 24: ...ot been purged and air is trapped in the gas line NOTE Blue smoke produced by the heat exchanger during the initial burner firing is caused by a thin film of oil on the surface of the heat exchanger T...

Page 25: ...e After approximately 30 seconds the control energizes the indoor blower on high speed To maintain the indoor temperature at the desired setpoint the thermostat may operate the high fire gas heating c...

Page 26: ...fter defrost terminates when the outdoor coil should be clear of frost When the measured delta T during heating operation reaches the calculated initiate delta T the demand defrost control DFC opens t...

Page 27: ...he inside of the burners and the burner ports for deposit buildup and corrosion Wipe and brush the inside of the burner and the burner ports and then clean with a dry cloth If the deposit buildup or c...

Page 28: ...fast flashes is 3 seconds Status LED Liteport LED IGN Diagnostic Indicators Flash Codes Figure 23 ECM Fan Control ECM Fan Motor Adjustments If the airflow needs to be increased or decreased see the A...

Reviews: