Verify discharge gas connection has isolation valve 

 

Discharge Gas Connection is connected to ZEVAC in a secure fashion 

 

Discharge Gas piping / hoses have been verified to be leak-free 

 

Discharge Gas piping has an isolation valve 

 

Verify hose halters are in place on ZEVAC discharge gas hose. 

 

 

Fluids 

Step  Check Description 

 

Verify Air Lubrication Fluid has adequate level. Add fluid if necessary. 

 

Verify Air/Water separator is empty and drain is not obstructed. 

 

Verify Air Filter drain is not obstructed. 

 

 
Visual Inspection 

Step  Check Description 

 

Verify the unit has not been damaged during shipping and handling 

 

Open the front panel and inspect the internal assembly 

 

Verify all connections are tight and all hose connections are secured 

 

Verify all safety controls are in place and properly connected. 

 

 

STARTUP 

Pre-Startup Purge (First Startup) 

In order to avoid the mixture of air and flammable gases, it is required to purge the ZEVAC® of 
air before introducing other gasses. Purging can be accomplished with inert nitrogen. The 
procedure for performing this purge is listed here: 

Step  Check Description 

 

Connect an inert gas such as Nitrogen to the Gas Intake piping 

(“Tree”)

 

 

Open Discharge Gas Vent / Dump Valve 

 

Open Nitrogen supply to flow into the ZEVAC® 

 

Open the Air connection to actuate the ZEVAC®  

 

The ZEVAC® will move Nitrogen through the system and out the discharge vent 

 

Continue purging with the ZEVAC® running for 30 seconds 

 

Verify 0% oxygen present in the vent gas stream 

 

Purging complete, disconnect Nitrogen 

 

Do not allow air to re-enter the system 

 

*The equipment can be purged with other gases in a similar fashion if nitrogen is unavailable. 

Routine Startup 

Step  Check Description 

 

Summary of Contents for ZEVAC

Page 1: ...SAFETY OPERATION MAINTENANCE AND STORAGE OF THIS PRODUCT BEFORE USE READ CAREFULLY AND UNDERSTAND ALL CAUTIONS WARNINGS INSTRUCTIONS AND PRODUCT LABELS FAILURE TO DO SO COULD RESULT IN SERIOUS PERSONA...

Page 2: ...roduced without written permission Keep this owner s manual handy so you can refer to it at any time The illustrations and procedures may vary according to the type If a problem should arise or if you...

Page 3: ...hout the approval of an authorized TPE representative CAUTION You must observe the instructions contained in this manual Failure to do so could result in physical injury damage or delays It is extreme...

Page 4: ...within the work area Hard hat Flame Retardant Clothing FRC Safety goggles preferably with side shields Protective shoes Protective gloves Hearing protection First aid kit NOTICE Never operate a unit...

Page 5: ...he maximum air pressure delivered to the ZEVAC Regulator contains a 5 8 Lock Nut and requires significant user effort to adjust wrenches at a minimum Air Control Valve Pilot Reset Manual Valve Pneumat...

Page 6: ...ck In the event that the gas suction pressure drops below the set point this control valve will prevent the ZEVAC from continuing to actuate Indicator Form Function Air Supply Pressure Panel Gauge Dis...

Page 7: ...ters are in place on all hose connections Inlet Connection DANGER Follow Lock out Tag out LOTO procedures for all process and energy connections WARNING All gas system components must be rated for the...

Page 8: ...ify all safety controls are in place and properly connected STARTUP Pre Startup Purge First Startup In order to avoid the mixture of air and flammable gases it is required to purge the ZEVAC of air be...

Page 9: ...tion 8 Verify smooth and normal ZEVAC Operation 9 Always monitor ZEVAC during operation OPERATION Step Check Description 1 Verify Gas Inlet pressure is dropping 2 Verify Gas Discharge pressure is not...

Page 10: ...using a crane Use only lifting equipment of suitable capacity for the size and weight of the lifted equipment The equipment must always be lifted using safe working practices and in accordance with an...

Page 11: ...erational and maintenance steps are complete After connecting the trailer to the tow vehicle check that the hitch assembly is latched Verify that the rear and tongue jacks are raised after the trailer...

Page 12: ...nly Ex approved spare parts and accessories that are authorized by an Ex approved TPE representative are used in Ex approved products Limitations The warranty does NOT cover defects that are caused by...

Page 13: ...position As the ZEVAC is evacuating gas the valve is allowing gas to enter the drawdown system and the pressure may not drop or may reduce more slowly than normal If the ZEVAC seems to be operating no...

Page 14: ...mporary condition Any sudden Bang or the non intermittent sound of gas being released is an indicator of an abnormal operating condition Follow SHUTDOWN procedure and call 1 855 ZEVAC GO for support a...

Page 15: ...to the device In the event that the ZEVAC unit cannot be accessed and needs to be shut down turn off the air supply 5 Always turn off the unit when making adjustments or changing connections 6 Inspect...

Reviews: