3. 

Emergency release of motor   

Swing gate operator SWING 225

•  If you need to release the motor for manual use, please 

proceed as follows:

•  Turn off power supply !

      

•  First,  remove  the  plastic  cover  lid  from  the  override 

mechanism, situated on the upper side of the operator. 

then insert the emergency override key and turn it max. 

2 turns counterclockwise.

•  Now the gate leaf can be slowly moved by hand (don´t try 

to move it faster than the motor would do).

•  To set the operator back into its normal operation mode 

please turn the emergency override key clockwise until a 

firm resistance can be felt.

•  Then put back the cover and turn on power supply.

2e.  Dis-installing the operator 

To dis-install the operator please follow the reverse installation procedure.

 

Before dismounting the operator please make sure that the power supply has been disconnected!

force adjustment  

on opposite side

opening

closing

+
–+

 

Warning

•  For force adjustment please turn valves smoothly, without bolting or unbolting them completely. Please note 

that the motors are delivered with already optimal force adjustment. 

•  To ensure optimal safety against crushes the shear force should only be slightly higher than necessary in order 

to move the leaves for opening and closing. The force measured at the end of the leaf should not exceed the 

nationally prescriptive limits. 

•  Never completely screw in the bypass valves. 
•  The operator is not equipped with electronic limit stops. Therefore the motors will stop when the adjusted travel 

time on the control board has expired. The operating time (travel time) has to be adjusted so that when the gate 

leaves meet the end stops on the ground it still runs for 5-10 seconds.

2d.  Force adjustment   

 for opening and closing 

Installation

•  Two force-adjustment-screws are situated on the lower side 

of the operator.

•  when turning 

clockwise

 the force will be increased

.

•  when turning 

counter clockwise

 the operator force will be 

decreased.

•  The forces for opening and closing have to be adjusted

Summary of Contents for SWING 225 AEB/29 N

Page 1: ...Installation and operating manual Swing gate operator SWING 225...

Page 2: ...ment The electric motor heats up during operation Therefore the device should only be touched after it has cooled off Please make sure that no other persons are on site of the motorised gate area espe...

Page 3: ...f the gate in the open and closed position and do normally not require the installation of an electric lock However on some installations it can be necessary to use an additional locking device e g an...

Page 4: ...perator the piston rod must NOT be completely driven to the limit min 5mm of spare travel In order to increase the strength of the connections we recommend reinforcing the welding brackets 1 2 with co...

Page 5: ...ditional electric lock has to be installed Furthermore the rear connecting bracket has to be very strong or supported in order to limit vibrations Opening to the INSIDE Center of rotation in line with...

Page 6: ...g bracket 1 should be reinforced with a corner plate 3 2b Installation of operator Installation after having installed the welding parts and corner plate 3 install the operator as follows Before mount...

Page 7: ...ty must be turned off from power supply when making the electrical connections For the connection with the control unit please check the corresponding manual For the connection of diverse safety devic...

Page 8: ...e side opening closing Warning For force adjustment please turn valves smoothly without bolting or unbolting them completely Please note that the motors are delivered with already optimal force adjust...

Page 9: ...f 50m For lengths 50m please use decoupling methods Only double insulated cables which are suitable for under ground usage e g E YY J may be used In case that special regulations require another type...

Page 10: ...mounting on the gate pillar column supported by gusset plate V respect a backdraft V 20mm of front and rear welding part 5 Dimensioned drawing Swing gate operator SWING 225 1 max travel285 67 67 with...

Page 11: ......

Page 12: ...Tousek GmbH Germany D 83395 Freilassing Traunsteiner Stra e 12 Tel 49 86 54 77 66 0 Fax 49 86 54 5 71 96 info tousek de Tousek GmbH Switzerland CH 6275 Ballwil Bahnhofstra e 14 Tel 41 0 41 448 2965 Fa...

Reviews: