6-INSTALLATION INSTRUCTIONS
1) After unloading the lift, place it near the intended installation location.
2) Remove the shipping bands and packing materials
from the unit.
3) Remove the packing brackets and bolts holding the
two columns together. Check to ensure all parts
arrived according to the parts list.
4) Once the lift location is decided, chalk the center line
in the bay and ensure that the proper lift placement
is observed from walls and obstacles. Also check the
ceiling height for clearance in this location.
NOTE:
the power unit column can be placed
on either side.
5) Assemble the overhead crossbar for model HD2P-9KCL. This is also a good time to
mount the brackets for the safety shut-off bar, the bar itself, and the shut-off switch. (Be
sure to leave bolts hand-tight.)
6) Position the columns facing each other 132.25” from the outside of the base plates,
then raise each carriage to the first safety lock.
NOTE:
The power unit column is referred
to as the main side column and the non power unit column is referred to as the offside
column.
7) Using a 3/4” concrete drill bit, drill the anchor holes in the main side column, installing
anchors as you go (see Fig. 11, page 31). Use a block of wood or rubber mallet to drive
anchor bolts in.
8) Using a level , check column for side-to-side plumb and front-to-back plumb. Using
3/4” washers or shim stock, place shims as close as possible to the hole locations as
needed. Torque 3/4” anchor bolts to
85 ft-lbs.
NOTE:
DO NOT USE IMPACT WRENCH.
9) Using a tape measure, measure diagonally from the face of one column to the opposite
face of the other to ensure that the columns are square (see below). After confirming
the dimensions, install the overhead crossbar to the top of the columns (hand-tight).
BEFORE drilling the anchors for the offside column, ensure the column is square and
double check measurements. Drill the anchor holes in the offside column, installing
anchors as you go. Check front to back and side to side plumb before torquing anchors
to
85 ft-lbs.
Use
shims
as
needed.
*As a reference - the distance between columns should be 110�25” at the top and at
the bottom of the lift�*
PLEASE READ THIS INSTRUCTION BEFORE STARTING TO OPERATE THE LIFT.
105.50”
18.00”
13.50”
110.25” (Face of Column)
Summary of Contents for HD2P-9KCL
Page 25: ...22 FIG 2 HD2P 9KCL Column Anchor Bolts 3 4 5 50 Column 4 Concrete 3000PSI min Torque Nut...
Page 27: ...24...
Page 36: ......
Page 37: ...NOTES...
Page 38: ...NOTES...
Page 39: ...NOTES...