2. Power Distribution Module
A.
Identify the two long “T” joists that
support the Power Distribution Module
(electrical control box). These will
have two pairs of opposing screw
holes for fastening the mounting
straps. They should be installed so
that the control box will be positioned
in the correct ceiling grid.
B.
Power Distribution Module (PDM)
Assembly:
Mount Power Distribution
Module box to ceiling joists with
opposing tapped screw holes, using
Control Box Mounting Straps. To
complete the switch circuit, attach the yellow cable from the Control Panel (extending from the vertical fame: see
yellow cord in diagram above), to the connector labeled “To Switch Connection” on the PDM.
C.
Recheck the frame to ensure that the structure is square. Then tighten all set screws.