Page 4-42
4.3 1RU Fiber Installation
4.3.1 1RU Splicing
The paragraphs that follow contain installation and routing procedures required for splicing IFC to
network elements in a 1RU LCX Splice Panel.
4.3.1.1 Installing & Routing IFC Fiber
An optional cable clamp is required for installing the IFC to an LCX Fiber Splice Panel. (See
“Accessories” on page 49.)
1. Route IFC to a rear corner entrance of the LCX Fiber Splice Panel, as shown in Figure 48.
You can route the IFC from the bottom up or top down at either rear corner of the
splice panel.
2. From a point approximately 2 in. (50 mm) just above or below the panel, measure out an ad-
ditional 70 in. (1778 mm) and then trim the excess IFC.
3. Before clamping the IFC to the rack, strip away the sheathing from this last 70 in. of the IFC
to expose subunits.
4. Assemble the cable clamp, as shown in Figure 43.
Figure 48 - IFC Breakout Length (1RU)
Breakout Point
70 in. (1778 mm) of Breakout for
Subunit Storage & Splicing
REAR VIEW
IFC
2 in. (50 mm)
Minimum