Solo Plus Instructions 1-800-782-9927 Version 12-13
Tarm Biomass · 4 Britton Lane · Lyme, NH 03768
3.5.4 Combustion and Performance Testing
The boiler should be fired to test for performance, using
Section 4.0
as a guideline.
Provision should be made for dissipating the heat generated.
Have enough fuel to complete an entire testing program.
Verify control strategy
Check that the boiler thermostat is functioning. Check the overheat thermostat, a temporary connec-
tion is made between terminals 5 and 6 on terminal strip Xl
(see circuit diagrams Section 6)
.
The fan
must switch off when the boiler reaches the temperature at which the overheating thermostat is trig-
gered. (The temporary connection between terminals 5 and 6 must be removed when the overheating
thermostat has been checked). The overheat thermostat can be switched on again when the tempera-
ture has fallen by about 60 ºF (15 °C) after 10-15 minutes. The unlocking knob (H)
(see Fig. 4.1)
is
located under a protective cap.
Boiler Installation & Start-up > Combustion and Performance Testing
Page 33