Y-6
Y-6
Assembly Adjustment (Crane Operation)
34
WY05-4191E
Y-6 Assembly Adjustment (Crane Operation)
1. Adjusting boom telescoping wire ropes
1. After assembling each boom section and adjusting the slide plate by adding or removing shims, retract the
boom fully. (Keep the wire rope free.)
[NOTICE]
Loosen the sway stopper bolt (see Y-6 1.5.) on the lower part of each boom section until it is out of contact
with the support.
2. Tighten the right and left adjustment nuts for the top boom section extension wire rope alternately. Pull out
the top boom section for 5 to 10mm (0.2 to 0.4in).