3. Commissioning
3.1 General
Commissioning sequence:
1. Check that there are no foreign objects inside the unit, duct
system or functional sections.
2. Turn the safety isolating switch to the ON position (I).
3. Select the appropriate language, if you have not already done
so. See Section 4.7 in the GOLD Function Manual, Installation
4. The air handling unit has a factory setting that makes it ready
to operate. See separate Commissioning Record.
However, in many cases, these settings need to be adjusted to
suit the current installation.
If necessary, enter the fan position setting (inspection side),
see Section 4.10 in the Function Manual, Installation.
Program the time switch, operating mode, temperatures,
airflows and functions according to Section 4 in the Function
Manual, Installation.
Select whether the airflow unit of measurement shall be l/s,
m
3
/s, m
3
/h or cfm.
Fill out the Commissioning Record and save it in the docu-
ment pocket of the air handling unit.
In some cases it might be necessary to adjust the P-band
and the I-time if the heating regulation system is oscillating
or operates sluggishly. This requires entering a special code.
Contact your Swegon representative.
5. Activate, if needed, manual or auto operation (Dashboard) or
lock the speed of the fans (AIRFLOW ADJUSTMENT image).
Adjust the duct system and the air diffusers according to Sec-
tion 3.2.
6. Check and adjust, if required, the pressure balance in the air
handling unit according to Section 3.3.
7. Finish with filter calibration according to Section 3 in the Func-
tion Manual, Installation.